HomeMy WebLinkAboutPackets - Council Packets (1755)Town Council Meeting
Regular Session
November 16, 2022
Town Council Meeting
Announcements
Upcoming Meetings
Meetings are subject to change. Check the Town website for meeting status.
Stormwater Utility Commission Meeting
November 17 at 4 p.m.
Hopi Conference Room
Board of Adjustment –CANCELED
November 22 at 3 p.m.
Council Chambers
Planning and Zoning Commission
December 6 at 6 p.m.
Council Chambers
Town Council Regular Session
December 7 at 6 p.m.
Council Chambers
4
Town Council Meeting
Regular Session
November 16, 2022
Spotlight on Youth
Laine Brchan
7th grade
Casas Christian Church
Finn Gardea-Gregg
4th grade
Casas Christian Church
6
Town Council Meeting
Regular Session
November 16, 2022
Town Council Meeting
Regular Session
November 16, 2022
Fiscal Year 2022/23
Financial Update Through September 2022
November 16, 2022
Overview/Reminders
All amounts are preliminary, unaudited and subject to change.
Year -end estimates may not include adjusting audit entries required at year-end.
Year -end estimates should not be relied upon as precise predictors of year-end balances;
they are fluid, informational, and based on currently available data.
The Town’s financial performance throughout the fiscal year is best indicated by
comparing actuals to the adopted budget.
Overall, revenues are performing well compared to budget, and expenditures are trending
as expected.
11
GENERAL FUND REVENUES
REVENUE SOURCE Budget Actuals
Thru 9/2022 % of Budget Year -End
Estimate Notes
Local Sales Taxes $ 25,270,959 $ 6,404,411 25.3%$ 26,528,407 Higher than expected growth in contracting sales tax,
retail, restaurant & bar, hotels, and remote seller
State Shared Revenues 17,605,693 4,095,624 23.3%18,246,957 Trending higher than expected in state sales tax
Charges for Services 3,046,515 751,672 24.7%2,953,483 Trending as expected
Licenses & Permits 2,223,824 421,839 19.0%2,483,824 Year -end estimate reflects revised commercial
permit revenue
Grant Revenue 455,000 127,384 28.0%472,000 Year -end estimate reflects transit federal grant
revenue
All Other 2,137,000 614,875 28.8%2,476,845
Includes other intergovernmental revenue, interest
income and miscellaneous revenue. Revised upward
due to $320K AMRRP rebate.
TOTAL GENERAL FUND
REVENUES $ 50,738,991 $ 12,415,805 24.5%$ 53,161,516 Favorable budget variance of $2.4 million projected
at this time 12
GENERAL FUND EXPENDITURES
EXPENDITURE CATEGORY Budget Actuals
Thru 9/2022 % of Budget Year -End
Estimate Notes
Personnel $ 34,876,210 $ 7,018,471 20.1%$ 34,907,842
Trending as expected; percentage of budget reflects
timing of payrolls as well as pension contributions
pending updated actuarial reports. Year-end estimate
attributable to Town Manager turnover, partially
offset by expected vacancy savings.
Operations & Maintenance 11,809,548 3,223,864 27.3%12,811,256
Actuals and year-end estimate include $885K claim
settlement payment for the Vistoso Trails Nature
Preserve. Year-end estimate also includes on-call plan
review services tied to commercial development.
Capital 1,387,725 78,245 5.6%1,387,725
Budget includes Westward Look improvements, IT
needs, and various departmental equipment and
capital needs
Transfers Out 16,446,977 2,048,965 12.5%16,446,977 Actuals reflect the budgeted transfer for debt service
TOTAL GENERAL FUND
EXPENDITURES $ 64,520,460 $ 12,369,545 19.2%$ 65,553,800 Budget variance of $1 million attributable primarily
to Vistoso settlement payment 13
Budgeted Use of Fund Balance:
($13.8M)
Estimated Use of Fund Balance:
($12.4M)
Estimated Ending Fund
Balance: $18.0M
37.4% of budgeted expenditures
Exceeds Council 25% Policy by
$6.0M
GENERAL FUND
$9.4M
$18.9M
$12.4M $12.4M
$50.7M
$64.5M
$M
$10M
$20M
$30M
$40M
$50M
$60M
$70M
Revenues Expenditures
General Fund
FY 22/23 Through September
PY Actual
CY Actual
CY Budget
14
HIGHWAY FUND REVENUES
REVENUE SOURCE Budget Actuals
Thru 9/2022 % of Budget Year -End
Estimate Notes
Licenses & Permits $ 25,000 $ 8,548 34.2%$ 25,000 Trending higher than expected, year-end estimate may
be revised as fiscal year progresses
State Shared Revenues 4,127,100 968,170 23.5%4,127,100 Trending slightly less than expected
All Other 11,000 22,434 203.9%15,000 Favorable budget variance of $4,000 due to a vendor
refund
TOTAL HIGHWAY FUND
REVENUES $ 4,163,100 $ 999,152 24.0%$ 4,167,100 Favorable budget variance of $4,000 or 0.1% due to a
vendor refund
15
HIGHWAY FUND EXPENDITURES
EXPENDITURE
CATEGORY Budget Actuals
Thru 9/2022 % of Budget Year -End
Estimate Notes
Personnel $ 1,202,574 $ 260,768 21.7%$ 1,202,574 Trending as expected; percentage of budget reflects
timing of payrolls
Operations &
Maintenance 823,615 177,280 21.5%823,615 Trending as expected
Capital 2,619,000 -0.0%2,619,000 Pavement preservation program to begin in October
TOTAL HIGHWAY FUND
EXPENDITURES $ 4,645,189 $ 438,049 9.4%$ 4,645,189 No budget variance projected at this time
16
Budgeted Use of Fund Balance:
($489,000)
Estimated Use of Fund Balance:
($485,000)
Estimated Ending Fund
Balance: $722,000
HIGHWAY FUND
$1.0M
$.6M
$1.0M
$.4M
$4.2M
$4.7M
$.0M
$.5M
$1.0M
$1.5M
$2.0M
$2.5M
$3.0M
$3.5M
$4.0M
$4.5M
$5.0M
Revenues Expenditures
Highway Fund
FY 22/23 Through September
PY Actual
CY Actual
CY Budget
17
COMMUNITY CENTER FUND REVENUES
REVENUE SOURCE Budget Actuals
Thru 9/2022 % of Budget Year -End
Estimate Notes
Contracted Operating
Revenues $ 3,980,149 $ 755,148 19.0%$ 3,980,149 Trending as expected
Town Operating Revenues 887,800 187,033 21.1%887,800
Recreation program revenue is seasonal; member
dues slightly below budget and less than prior year
actuals
Other Revenues 3,639,386 830,217 22.8%3,766,005
Includes ½ cent sales tax revenues, HOA
contributions, interest income and other
miscellaneous revenues. Trending slightly higher
than expected due to ½ cent sales tax.
TOTAL COMM. CENTER
FUND REVENUES $ 8,507,335 $ 1,772,399 20.8%$ 8,633,954 Favorable budget variance of $126,619 due to sales
tax revenue
18
COMMUNITY CENTER FUND EXPENDITURES
EXPENDITURE CATEGORY Budget Actuals
Thru 9/2022 % of Budget Year -End
Estimate Notes
Contracted Operating
Expenditures $ 4,723,618 $ 1,102,054 23.3%$ 4,723,618 Trending as expected
Town Operating
Expenditures 1,695,573 361,569 21.3%1,695,573 Trending as expected
Capital Outlay 2,666,700 220,615 8.3%2,666,700 Projected on budget at this time
Transfers Out 4,085,380 2,028,066 49.6%4,408,520
Actuals reflect the budgeted transfer for debt
service; year-end estimate includes transfer out of
all estimated fund balance in excess of $1 million to
Capital Fund for golf irrigation project
TOTAL COMM. CENTER
FUND EXPENDITURES $ 13,171,271 $ 3,712,304 28.2%$ 13,494,411 Budget variance of $323,140 or 2.5% due to
transfer out for golf irrigation project
19
COMMUNITY CENTER FUND
Budgeted Use of Fund Balance:
($4.7M)
Estimated Use of Fund Balance:
($4.9M)
Estimated Ending Fund
Balance: $1M$1.8M $1.6M$1.8M
$3.7M
$8.5M
$13.2M
$M
$1M
$2M
$3M
$4M
$5M
$6M
$7M
$8M
$9M
$10M
$11M
$12M
$13M
$14M
Revenues Expenditures
Community Center Fund
FY 22/23 Through September
PY Actual
CY Actual
CY Budget
20
MONTHLY FINANCIAL UPDATE
QUESTIONS?
21
Town Council Meeting
Regular Session
November 16, 2022
Intergovernmental Funding Agreement
between the RTA and Oro Valley
for Naranja Drive Multi-Use Path
La Cañada Drive to First Avenue
November 16, 2022
Overview
This intergovernmental transportation funding agreement (IGA) between the Regional
Transportation Authority (RTA) of Pima County and the Town of Oro Valley will provide
funding in the amount of $208,417 for the Naranja Multi-Use Path project.
This project is funded by Federal Regional Transportation Alternatives Grants (RTAG) in
the amount of $3,448,017 or 94.3% of the total project cost. The RTA will provide funds in
the amount of $208,417 or 5.7%, which are the required local matching funds.
In accordance with the requirements regarding the use of federal funds, the Arizona
Department of Transportation (ADOT) will administer the implementation of the Naranja
Multi-Use Path project (design, construction and overall administration).
27
Funding Detailed Information
Federal law delegates PAG to serve as grant administrator for the Federal Transportation Alternatives program, known regionally as “Regional Transportation Alternatives Grants (RTAG).”
On May 3, 2022, PAG announced a Call for Projects for the PAG Fiscal Year 2023-2026 competitive Regional Transportation Alternatives Grants (RTAG).
Projects had to meet both eligibility criteria for federal requirements for the RTAG program and the RTA categorical #41 (greenways, pathways, bikeways and sidewalks).
RTAG federally funded projects must be selected through a competitive process.
The RTA would fund the 5.7% matching fund.
Staff applied for the Naranja Drive Multi-Use Path project between La Cañada Drive and First Avenue.
Project was selected and awarded $3,448,017 in RTAG funding and $208,417 in RTA funding to be used as part of the 5.7% non-federal matching funds.
Because the Town of Oro Valley is not a federally fund certified agency, the Arizona Department of Transportation (ADOT) will administer projects on behalf of a non-Certification Acceptance applicant. This includes implementation of the project (design, construction, and overall administration), in accordance with the requirements regarding the use of federal funds.
Therefore, a separate Intergovernmental Agreement (IGA) between the Town of Oro Valley and the Arizona Department of Transportation (ADOT) will be brought to the Town Council for approval later this year. This IGA must be executed prior to the authorization of federal funds and initiation of the project.
28
Naranja Drive Multi-Use Path Project
29
Detailed Project Information
Approximately 2 miles long from La Cañada Drive to First Avenue
10’ wide asphalt multi-use path
Path will be on the north side of Naranja Drive (within public right-of-way)
Several major cut and fill areas
Culvert extensions
New multi-use path will link to the multi-use paths on La Cañada Drive and First Avenue
Provide access to Naranja Park
Total cost estimate: $3,656,434
30
Questions?
31
Town Council Meeting
Regular Session
November 16, 2022
Vistoso Trails Nature Preserve Master Plan
November 16, 2022
Master Planning Background
Vistoso Trails Nature Preserve
July 15, 2022, Town of Oro Valley hosts ribbon cutting ceremony for the Vistoso
Trails Nature Preserve.
Request for Proposal for Master Plan services was published in July 2022; three
submittals were received in August 2022.
Sites Southwest was awarded the contract in September 2022.
Sites Southwest Project Managers:
Liz Cole and George Radnovich
34
Master Plan Goals and Objectives
Vistoso Trails Nature Preserve
Create a plan based on input received from the community.
Develop a plan that is a dynamic document and fully compliant with the requirement of the conservation easement.
Create a plan that can be implemented in phases.
Develop a habitat management plan.
Develop education programs that celebrate the site’s cultural and environmental resources; focus on development of a volunteer docent program.
Provide access for a variety of users that include walkers, cyclists, bird watchers, school groups, eco-tourism, etc.
35
Community Engagement
Vistoso Trails Nature Preserve
Stakeholder meetings
Town Council
Town staff
Parks and Recreation Advisory Board
School Principals
Community groups
Conservation groups
•Community Meetings
•Parks and Recreation Advisory Board meeting (11/25/22)
•Community workshop (11/16/22)
•Town Council meeting (11/16/22)
•Community meeting (11/17/22)
•Community survey (11/4 –30/22)
•Community workshop (January 2023)
•Parks and Recreation Advisory Board meeting (February
and April 2023
•Town Council meeting (March and May 2023)
36
Vistoso Trails Nature Preserve
Master Plan
Sites Southwest was founded in 1997 in Albuquerque,New Mexico to provide clients throughout the
Southwestern United States with planning,landscape architecture,and urban design services.We are an SBA-
certified small business based in New Mexico with offices in Albuquerque,El Paso,and Bend,Oregon.
We believe that great places are created by carefully and collaboratively integrating site,environment,and
culture.We understand and value our region’s diverse ecosystems,cultures,traditions,and environments.
Our mission is to significantly improve the communities in which we work.
OUR TEAM
Blending the skills of planners,designers,and educators,The Acorn Group offers award-winning services in interpretive
planning and design.Part art,part science and history,accented with storytelling and design,our interpretive master
plans,exhibits,panels,and programs create sensory-rich experiences that bring content to life.Established in 1990 and
nationally certified as a Woman Business Enterprise,The Acorn Group works with a range of clients from government
agencies to private and non-profit institutions.Project sites include visitor centers,museums,public gardens,ecological
reserves,parks,and educational institutions.Our greatest satisfaction comes from seeing plans and drawings become
reality and watching visitors take delight in new experience.
BACHECHI OPEN SPACE AND TRAIL MASTER PLAN
Our Team’s Relevant Project Experience
The refuge’s goals include attracting waterfowl and other avian species to xeric and mesoxeric landscape habitats.
VALLE DE ORO MASTER PLAN
Sites Southwest received three awards for our work onHighDesert,including theAmericanSocietyof Landscape Architects’New Mexico Chapter’s 2006 DesignAward.
HIGH DESERT COMMUNITY
The Acorn Group’s projects and efforts have beenrecognizednationally,receiving such awards as theExhibitDesignAward,Print and Media Award,andInterpretiveMediaAwardbytheNationalAssociationforInterpretation,Award of Excellence by the American Society ofLandscapeArchitects,Best of Show by theWesternFairsAssociation,Award of Excellence by theCaliforniaParksandRecreationSociety,andNationalEducationAwardbythe Association of ZoosandAquariums.
•Big Basin Redwood State Park
•Borrego Village Association
•Cabrillo Marine Aquarium
•Compton Creek Natural Area
•George F Canyon Nature Center
•North Carolina Botanical Garden
•Silver Creek Preserve
•Coral Mountain Discovery Park
•Anza-Borrego Desert State Park
•Holden Forests and Gardens
VISTOSO TRAILS MASTER PLAN
The goal of the master plan process is to create a working document that addresses:
•The long-term protection of the site ecological and cultural resources.
•Providing educational opportunities for a wide-range of user groups that is inclusive of all ages and
abilities.
•Creating site-sensitive passive recreational attributes that blend the built environment within the
natural surroundings.
The two hundred and two (202)acre Vistoso Trails
Nature Preserve presents the beauty of the Sonoran
Desert teeming with wildlife and artifacts of the Native
Americans who lived and hunted there.The existing
6.2-mile,eight-foot-wide concrete path winds through
the property providing visitors with views of the
Catalina and Tortolita mountains,examples of varied
desert vegetation,and the opportunity to view an
abundance of wildlife.With easy access from multiple
locations,visitors can stroll the property and connect
with the natural world we tend take for granted.
Stakeholder Input Received to Date
2022 Stakeholder Interviews
Conducted from October 4, 2022 –November 3, 2022
Programming Suggestions:
•Create a system of looped walking/biking trails
•Provide natural surface trails for running and walking
•Create separate areas for wildlife viewing
•Provide spaces for family gatherings
•Include sculpture and public art
•Provide shade and seating areas
•Create educational gardens and signage
•Provide dispersed parking areas and directional signage
•Address wash area erosion and safe crossing concerns
•Create areas for nature play
•Provide programming for habitat and dark sky viewing
•Connect the Preserve trail to the Town trail system
•Create natural structures and water features to support habitat
•Re-establish native vegetation throughout the Preserve
•Develop operations and management protocols
Next Steps
Community Engagement Timeline
•Tuesday, November 15, 2022
Parks and Recreation Advisory Board Meeting at 6 p.m.in the Hopi Room
•Wednesday, November 16, 2022
Community Workshop between 10:30 a.m. and 5 p.m. at the Oro Valley Public Library
Town Council Meeting at 6 p.m.in Council Chambers
•Thursday, November 17,2022
Community Meeting at 6 p.m. in Council Chambers
Project Timeline
•November -December 2022
1. Site Research and Data Gathering
2. Stakeholder Meetings
3. In-person Meetings and Workshop
4. Questionnaire
5. Findings Report
•January –March 2023
1. Draft Master Plan -Presented to Community via Community Workshop and Meeting (January)
2. Draft Master Plan -Presented to Parks and Recreation Advisory Board (February)
3. Draft Master Plan -Presented to Town Council (March)
•April –May 2023
1. Final Master Plan -Presented to Parks and Recreation Advisory Board (April)
2. Final Maser Plan -Presented to Town Council (May)
For more information, contact:
Sites Southwest
505.822-8200
lcole@sites-sw.com
Questions & Comments
Town Council Meeting
Regular Session
November 16, 2022
Parks Bond Projects
Value Engineering Update
November 16, 2022
49
October 5 Council Presentation: Bond Projects Financial Overview
At this meeting the following financial summary was presented:
The current total cost of all projects associated with the bond is:
• Naranja Park Expansion $ 33,665,457 (Contracted & Estimated)
• Golf Irrigation Replacement $ 9,153,218 (Contracted)
• Tennis Courts Replacements $ 2,921,044 (Contracted)
• Community Center Parking Lot $ 2,000,000 (Estimated)
• Multi-Use Paths $ 3,620,000 (Contracted & Estimated)
Total Cost $ 51,359,719
The current funding sources provide the following:
• Parks & Recreation Bond $ 25,000,000
• Community Center Fund $ 2,100,000
• ARPA $ 4,623,498
• RTA $ 420,000
• Federal Grant $ 1,000,000
Total Funding $ 33,143,498
This created a shortfall, between total costs and total funding, of $18,216,221.
Current Naranja Park Site Plan
50
Value Engineering/Mitigation Plan to Close Shortfall
Naranja Park Expansion: Reductions of $12,037,392:
Utility Material Long Lead Items –Reduction in scope of amenities causes reductions in utility mains being installed at this time, as well as elimination of two fields has caused a reduction in construction materials ordered here.
Reduces costs by $474,343
Infrastructure Work –same as “Utility Material Long Lead Items.”
Reduces costs by $691,606
Musette Road –No work to existing asphalt, replace new asphalt with double shot chip-seal and slurry seal, reductions in curbing and site walls.
Reduces costs by $1,886,226
Skate Park, Pump Track, Basketball –Defer basketball courts, limit construction of wheel park to $500K, dirt pump track limit construction to $200K, remove shade sails, relocate to northern pad, curb and parking reductions. Will still require a restroom at the northern pad.
Reduces costs by $1,313,162
Splash Pad –Reduced the budget for the splash pad by half and redesign to new budget, reduced the budget for the shade sails by half and redesign to new budget, and removed the restroom and ramada.
Reduces costs by $1,496,189
51
Value Engineering/Mitigation Plan to Close Shortfall
Naranja Park Expansion Reductions (cont):
Pickleball –Reduce the number of courts to be built from 6 to 4, remove ramada, and associated hardscape reductions.
Reduces costs by $329,996
Parking -Replace new asphalt with double shot chip-seal and slurry seal except within handicapped parking areas, reductions in curbing and site walls.
Reduces costs by $2,087,217
Ops & Maintenance Center –Defer maintenance operations building and associated elements, lighting reductions, pavement reductions and fencing material reductions (replacing masonry wall with chain-link).
Reduces costs by $1,155,673
Multi-Use Fields –Defer the construction of fields 7&8, including lighting and associated hardscape reductions, no landscaping, and remove one ramada.
Reduces costs by $1,893,300
Dog Park –Do not relocate. Leave as is, no improvements/changes planned as a part of this Bond project.
Reduces costs by $709,680
52
Value Engineering/Mitigation Plan to Close Shortfall
Golf Irrigation Replacement: Reduces overall cost by $400,000
Phase 1 Contingency savings = $400,000
Tennis Courts Replacement: Reduces overall cost by $172,590
Contingency savings = $172,590
Community Center Parking Lot: Reductions of $1,400,000
Reduce scope to just clearing, regrading, and paving only the dirt lot = $1,400,000 in Bond reductions
Multi-Use Paths: Reductions of $3,362,410
La Cañada path –Keep on the west side to utilize RTA funding, only construct the gap area with MUP, defer the remaining
MUP = $862,410 in cost reductions
Naranja path –Now completely funded by outside sources = $1,000,000 in cost reductions
CDO to JDK path –Defer until later = $1,500,000 in cost reductions
53
Summary of Savings
The total reductions from all the above measures are
$17,372,392
This reduces the overall costs to $33,987,327
Comparing to the following funding:
•Parks Bond $ 25,000,000
•Community Center Fund $ 2,100,000
•ARPA $ 4,623,498
•RTA Removed –realized within the savings
•Federal Grant Removed –realized within the savings
Total Funding $ 31,723,498
The calculated shortfall = $2,263,829
This is without contingency for the Park Project, Parking Lot and MUP’s
54
Staff recommends adding a 5%
contingency on:
Naranja Park Expansion
Community Center Parking Lot
Remaining MUP
This is an additional $900,000.
Shortfall Request:
$3,163,829
Note –You may notice that we used exact numbers throughout the presentation and on previous Council
Reports. This is easier to follow the data used to create this information. In the end, we should round, such as
the Shortfall Request to $3,200,000 as much of the data included to get to this point is estimated.
Direction Moving Forward
With all the value engineering measures recommended plus a 5% contingency added in for:
Naranja Park Expansion
Community Center Parking Lot
La Canada MUP
Note -Golf Irrigation Phase 2 Replacement already has a 10% contingency within the budget
The project shortfall has been reduced from $18,216,221 to $3,163,829.
This shortfall could be drawn from current available reserves. Any of the unused $900,000 contingency would reduce the amount needed from available reserves.
In addition, there are $500,000 in Parks Impact Fees available that could reduce the use of available reserves or be used as additional contingency.
What is Council’s direction?
55
Town Council Meeting
Regular Session
November 16, 2022
Community Center
ADA Accessibility Update
November 16, 2022
Community Center ADA Access Update
During the April 6, 2022, Town Council meeting, staff was directed to bring
Town Council a proposal to add an elevator or appropriate technology to the
existing building in the most cost-effective way, while keeping the existing
entrances, restaurant location and building functions. It was made a priority
from existing Community Center funds and the $750,000 set aside for this
purpose.
Since that direction was given, staff has been working toward the following:
Action items discussed at this meeting were for the condition of the rear ramp, second floor back
access door and additional handicapped parking
Analysis and creation of alternatives to provide a formal ADA accessible routing to all three floor levels
75
Council Immediate Action Items
Existing ramp providing access to the second floor from the current ADA parking
spaces
Have created a sweeping schedule in the interim until the concrete replacement is constructed
Have nearly finished the design of a concrete replacement
Working with a contractor to execute the concrete replacement
Addition of ADA parking spaces
Cannot under current parking lot configuration due to non-compliant slope issues
Electronically locked door at the top of the current ramp
Have check that it both works properly and that it is operationally ADA compliant with correct pull resistance
76
Alternatives to provide ADA accessibility to all three floor levels
For review, the Community Center has three levels, with main uses identified:
First floor –where the Golf Pro Shop/check-in, locker rooms, Parks & Recreation administration and
fitness reside
Intermediate level –not a complete floor story height above the first floor, houses the main golf side of
the building entrance and golf administration
Second floor –where the restaurant and Sunset Room reside
The Breckenridge Group (architect), reviewed several conventional methods of
routing, sought advice from a Parks & Recreation ADA specialist and conducted
focused user group review panels to discuss solutions to create new means of
providing ADA accessibility to all three floor levels of the Community Center.
77
Alternatives to provide ADA accessibility to all three floor levels
The study was broken down into the following elements:
Technology solutions –what is readily available to provide ADA access between floors
External access routing -Access from ADA-compliant parking to the building entrance
Internal access routing –Access within the building from the entrance to whatever technology is
provided to access between floors
Because these three study areas are somewhat independent of each other, a
summary table will be provided at the end of this presentation for Council to
consider the best alternative to implement a total solution.
78
Technology Solutions
Council directed staff to provide a proposal to add an elevator or
appropriate technology to the existing building in the most cost-effective
way
Conventional Elevator –Integrated and built into the building structure
Pros:
•Permanent solution used to provide access to building floors by allowing very flexible and high-capacity use
Cons:
•Cost –requires major building reconfiguration to create an elevator shaft, sump pit and HVAC
LULA -Limited Use/Limited Application Elevator –Two -to-four -person lift,
not hard built into the building structure (pictured to right)
Pros:
•Cost –inexpensive compared to a standard elevator
•Requires minimal to no building modification, as it provides its own shaft as a part of the appliance
•Can be sized for two-to-four-person use
Cons:
•Cost –second most expensive option, behind the Conventional Elevator 79
Technology Solutions
LULA Examples
80
Technology Solutions
Vertical Platform Lift –Two -person lift, not hard built into the building structure
Pros:
•Cost –Inexpensive
•Requires minimal to no building modificationCons:
•Unless treated with an enclosure, has an industrial aesthetic. With an enclosure, this becomes a LULA Elevator.
•Limited sizing –generally made to accommodate one to two persons.
Chair Lifts –Commercial version of the home use devices one sees in advertisements
Pros:
•Cost for appliance only
•Ease of installationCons:
•Single user
•Does not provide the ability to have a walker or wheelchair following user
•Speed of use
•May not be preferred by users in comparison to elevator-type access options
81
Similar to Chair Lifts are Inclined Wheelchair lifts that follow staircases. However, they do not offer as secure a seat as a conventional Chair Lift for non-wheelchair users (Below)
Technology Solutions
Stair Crawlers –Mechanical device that can
traverse a staircase
Pros:
•Extreme flexibility as it can be moved anywhere
Cons:
•Single user
•Does not provide independent use by ADA persons
•Generally used to move bulk cargo rather than passengers
•Very industrial aesthetic
82
External Access Routing
Alternative #1 –Existing second
floor entrance with the existing
ramp through the mechanical
yard to existing handicapped
parking.
Pros:
•Cost –no real building or grading
modifications required. Being cleaned up as
a part of the Council’s request, making this
the lowest-cost alternative.
Cons:
•This solution feels like a long ramp for the
user and is not easy to traverse for the
mobility impaired.
•Is not aesthetically pleasing as one traverses
through the mechanical/delivery yard.
•Users already express dissatisfaction about
this option.
83
External Access Routing
Alternative #2 –Existing front
entrance accessed from existing
handicapped parking with a ramp.
Pros:
•Lower cost than any solution that requires building
modifications.
Cons:
•Slightly more costly than the current ramp option, as
it requires the construction of a completely new
ramp.
•Has a long path of travel from the existing
handicapped parking spaces and the elevation
difference is similar to the existing ramp. Could be
considered a laborious path of travel for building
patrons.
•Does not allow for the creation of handicapped
parking closer to the entrance.
84
External Access Routing
Alternative #3 –Existing rear
entrance by Golf Pro Shop to
new handicap parking within
the golf cart staging area.
Staff is not suggesting one
circulation method over another
except -
Staff is not recommending this
solution as it is problematic
from both an ADA functional
standpoint and an operational
perspective.
85
External Access Routing
Alternative #4 –Existing fitness
entrance and circulating through
the building to the rear entrance
by the Golf Pro Shop.
Pros:
•Lower cost than any solution that requires
building modifications.
•Path of travel is at relatively the same grade.
Cons:
•Longest Path of travel for any of the
solutions.
•Control issues with the fitness center
operation as that is a membership control
point.
•Requires entering and exiting, and then re-
entering the building for path of travel.
86
External Access Routing
Alternative #5 –Lowering the
front entrance to enter at the
first floor and connecting to new
handicapped parking spaces at
the front of the building.
Pros:
•Provides the opportunity to create new
handicapped parking at the front entrance.
•With the creation of this new handicapped
parking adjacent to the entrance location,
renders the least path of travel length.
Cons:
•Most expensive exterior circulation
alternative as it requires building.
modification, porte cochere demolition and
parking lot grading to allow patrons to enter
at the first floor.
87
Internal Access Routing
Option #1 –Uses two dual-stop LULA
Elevators. One located near the Golf
Administration offices that accesses the first
floor and the intermediate floor. The other
LULA Elevator is near the Golf Pro Shop and
accesses the first and second floors. This
option works with exterior access
alternatives:
Alternative 1 -Existing second floor entrance with the
existing ramp through the mechanical yard to existing
handicapped parking.
Alternative 2 -Existing front entrance accessed from
existing handicapped parking with a ramp.
Alternative 4 -Existing fitness entrance and circulating
through the building to the rear entrance by the Golf Pro
Shop.
88
Internal Access Routing –Option 1
89
Internal Access Routing
Option #2 –uses a singular three-stop LULA
Elevator near the Golf Administration that
accesses all three floors and can be used with
the following exterior access alternatives:
Alternative 1 -Existing second floor entrance with the
existing ramp through the mechanical yard to existing
handicapped parking.
Alternative 2 -Existing front entrance accessed from
existing handicapped parking with a ramp.
Alternative 3 -Existing fitness entrance and circulating
through the building to the rear entrance by the Golf Pro
Shop.
90
Internal Access Routing –Option 2
91
Internal Access Routing
Option #3 –similar to option 1, except the
LULA Elevator is moved from next to the
Golf Pro Shop to behind the Hearth with
all the same exterior access alternatives:
Alternative 1 -Existing second floor entrance with the
existing ramp through the mechanical yard to existing
handicapped parking.
Alternative 2 -Existing front entrance accessed from
existing handicapped parking with a ramp.
Alternative 3 -Existing fitness entrance and circulating
through the building to the rear entrance by the Golf
Pro Shop.
92
Internal Access Routing –Option 3
93
Internal Access Routing –Lowered Front Entry –Option 1
94
Internal Access Routing –Lowered Front Entry –Option 2
95
Internal Access Routing –Lowered Front Entry –Option 3
96
Community Center ADA Access Update -Costs
None of the options have been estimated yet because preliminary designs have
not been completed for most.
This is a preliminary study to evaluate the best means for handicapped persons
to enter and circulate between the three floors of this facility. One of the
solutions presented:
Alternative 5 exterior access (lowered front entrance entering at the first floor and connecting to new
handicapped parking spaces at the front of the building) with a LULA 3-stop Elevator with interior
circulation. Option 2 does have a preliminary estimate created by a professional estimator.
Preliminarily this is estimated at $1.3M.
Staff had the estimator concentrate on this approach to confirm that whatever
option and configuration are selected, the Town will be able to afford the
project within the Council stipulated budget of $1.5M.
97
Summary Table -Relative Costs Comparison
98
Lift Device Interior Access Routing
Exterior Access Routing
Conventional Elevator
LULA Elevator
($200 to $400K)
Vertical Lift
($75 to 150K)
Chair Lift
Stair Crawler
Alternative 5
Lower Front
($700K to $1M)
Alternative 2
Ramp to Front
($150 to 300K)
Alternative 3
Parking in Rear
Alternative 1 or 4
Existing Routes
($0)
Option 3
2 Lift Devices
Option 2
1 Lift Device
Option 1
2 Lift DevicesCost
Represents the
Consultant
Estimator’s $1.3M
initial assessment
Community Center ADA Access Update –Public Outreach
Staff conducted two focused user group interviews. The alternatives were reviewed, and both rendered the same conclusion: install one LULA elevator accessing all three floor levels and lower the front of the building. Reasoning offered:
Offered closest parking
Ease of entering the building
Singular lift/LULA makes the most sense and is the nicest to use independently
Aesthetically pleasing for the facility
It was stated that this was the most inclusive option and most sense of belonging to the disabled community
However, this represents one of the most expensive configurations, less building a conventional elevator.
99
Community Center ADA Access Update Summary
100
There has been a standing budget CIP allotment of $750,000 for the installation of
an elevator into the Community Center. During the April 6, 2022, Council Meeting,
another $750,000 was added to the project from the Community Center Fund,
making the total project budget $1,500,000.
There is a balance between cost and ease of use.
One of the most expensive options, which still should be able to be contained within the budget allotment, is
the easiest and most useful for the patrons we asked.
The lesser viable cost options require longer travel distances and ramps, which has been historically
problematic for this ADA focus user group.
Staff is seeking Council direction to move forward and construct the desired
solution.