HomeMy WebLinkAboutOV1800362TOWN OF ORO VALLEY
COMMUNITY DEVELOPMENT & PUBLIC WORKS DEPARTMENT
11000 N. LA CANADA DRIVE, ORO VALLEY, AZ. 85737
PHONE: (520) 229-4800 FAX: (520) 742-1022
www.orovalleyaz.gov
1.2 GENERAL APPLICATION FORM
Apnliication
❑
TVp
Major General Plan Amendment
❑
Final Plat
Q
❑
Rezoning/PAD Amendment
❑
Pre -Application
❑
Planned Area Development
❑
Zoning Verification FEB O; 2Q18
®
Conditional Use Permit
❑
Sign Criteria
❑
Zoning Code Amendment
❑
Sign - PAD Exemption
❑
Conceptual Site Plan
❑.
Master Sign Program """""•••
❑
Conceptual Public Art
❑
Communication Facility -Tier 1 and 2 Minor
❑
Conceptual Architecture
❑
Communication Facility — Major
❑
Final Site Plan
❑
Revised Development Plan
❑
Conceptual Landscape Plan
❑ Other
Subject Property Information:
Address: Tangerine Rd. (Shannon Road — Cooper Mt. Drivel
Parcel/rax Code: N/A
Subdivision / Commercial Center Name: N/A
Book / Page or Sequence Number: N/A
Lot Number(s) N/A
Legal Description: S25' of N75' Sec 1 - 4 T12S R13E
Section/Township/Range: Sec 1-4, T12S. R13E
- Area of Property: 25' feet X 3.5 miles
Existing Land Use: overhead utility
Proposed Land Use: _overhead utility
Applicant
Information:
* If more than one, attach list
Applicant
*:
Name: Tucson Electric Power Co. Firm:
Address: _Land Resources — RC131. 3950 E. Irvington Road
City:
Tucson State: AZ Zip: 85714-211'4
Telephone: 520-300-0586-46— Fax: 520-770-6780 Email:
isaline(a)-tep.com
Property Owner(s) if different from Applicant *:
Name: _Town of Oro Valley Right -of -Way Firm:
Address:
Telephone: Fax:
Consultant: (Discipline)
City: _
Email:
State: Zip: _
Name: Firm:
Address: City: State: Zip:
Telephone: Fax: Email:
1
Project Descriation/Narrative: see attachment
hereby certify that I have read and examined this application and know the same to be true and correct. I am the owner
of the property or the Owner's authorized representative, and if not the owner, I have obtained the owner's permission to
perform stated work. All provisions of laws and ordinances governing this type of work will be complied with whether
specified herein or not. The approval of this application does not presume to give authority to violate or cancel the
provisions of any other federal, state or local law for which this project may be subject to.
Notice: It is the applicant/owner's responsibility to ensure all private rules and regulations (such as Covenants, Conditions
& Restrictions (CC&R's)) of the subdivision and/or commercial center are adhered to. Contact your Home Owners
Association or property management to determine applicable requirements.
It is also the applicant's responsibility to coordinate with all outside agencies to secure their acceptance or clearance.
Failure to do so may delay issuance of permits. See attached list of agencies.
NCSO1'1 Sc��� n�
a
plicant's Signature Print Name Date
Important Note: All submittals received after 4:00 p.m. will be processed the next day
Submittals will be rejected
• Not folded using Pima County fold & collated;
• There are missing items on the checklist unless otherwise approved by Planning and Zoning Administrator or Town
Engineer.
• Re -submittals cannot be accepted without a transmittal and a written response to staff comments.
2
TEP
Tucson Electric Power
Land Resources — RC131
3950 E. Irvington Road
Tucson, Arizona 85714-2114
138 Kilovolt Tangerine Road Transmission Line Upgrade
Tucson Electric Power (TEP) is planning to make necessary upgrades to a segment of an existing 138 kilovolt (kV)
transmission line that connects TEP's North Loop Substation, located near West Tangerine Road and Interstate 10,
to the Rancho Vistoso Substation, located near East Tangerine Road and North Copper Mountain Drive. TEP must
complete these improvements to continue providing safe, reliable service to customers in the area. A portion of this
work (The Project) will occur in Oro Valley within a 3.5-mile stretch of TEP's easement along the southern edge of
Tangerine Road between North Shannon Road and Copper Mountain Drive.
As part of the Conditional Use Permit application process, the following criteria has been provided by Tucson Electric
Power (TEP) to clarify any potential concerns for public health, safety, or welfare as a result of approval for the
proposed transmission line upgrade project.
Conditional Use Permit Criteria
1. Granting of such conditional use permit will not be materially detrimental to public health, safety, or
welfare. Factors which shall be considered have been addressed as follows:
a. Damage or nuisance arising from noise, smoke, odor, dust, vibration or illumination;
The Project will not result in an increase in noise, smoke, odor and illumination. The Project may
generate temporary dust emissions as a result of construction. Dust emissions will be mitigated
using water spray as necessary. Upon completion, the Project will not generate dust as a result of
the intended use.
Hazard to persons and property from possible explosion, contamination, fire or flood;
There are no health hazards identified to persons as a result of the Project. The Project will not
create any hazards associated with explosion, contamination, fire or flood. As a result of the
neighborhood meeting held on Wednesday January 24`h, TEP has provided information regarding
electric and magnetic field (EMF) levels associated with overhead 138 kilovolt transmission lines.
See attached.
c. Unusual volume or character of traffic,
During construction, the Project may temporarily impact the flow of traffic within the area.
Traffic impacts will be mitigated to the extent possible with an approved traffic control plan.
Upon completion, the Project will not impact daily traffic patterns.
2. That the characteristics of the proposed use are reasonably compatible with the types of use permitted in
the surrounding area and sufficient mitigation measures are employed to minimize impact on adjoining
properties.
a. The Project design and use aligns with the current type of use as permitted within the project
area.
b. TEP will cooperate with Oro Valley to minimize impacts to adjoining - properties -and apply
appropriate mitigation measures as necessary. i'4 '
FEB 0�,201�
TJY........................
3. That the proposed use is consistent with the goals and policies of the general plan.
a. TEP will coordinate with Oro Valley to ensure the Project is consistent with the goals and policies
of the general plan.
4. That the hours of operation of the proposed use will not adversely impact neighboring properties.
a. The hours of operation for the proposed use will not adversely impact neighboring properties.
New Utility Pole Criteria
1. A Conditional Use Permit for the erection of new utility poles and wires will be granted in accordance with
Section 22.5. The primary considerations shall be aesthetics with the following factors also considered.
a. The location and height of such poles and wires and the relation to the present or potential roads;
i. The Project design complies with national standards for transmission of electricity. In
addition, TEP will coordinate with Oro Valley Engineering Division to ensure location and
height of newly installed transmission poles will not adversely impact present or future
planned roadway improvements.
b. The crossing of such lines overmuch traveled highways and streets;
i. The need to crossover highways and streets during construction will be coordinated with
an approved traffic control plan as necessary.
c. Proximity of such lines to schools, religious institutions and other places where people may
congregate;
I. The project is adjacent to the St. Mark Catholic at 2727 W Tangerine Road. TEP will
cooperate with Oro Valley to avoid adverse impacts for events and flow of traffic during
normal operating hours of the church.
d. Fire or other accidental hazards from the presence of such poles and wires and the effect, if any, of
the some upon the effectiveness of fire fighting equipment; ,
i. TEP will replace all wooden poles with steel monopoles therefore reducing potential fire
hazards associated with wooden poles.
e. The availability of a suitable right-of-way for the installation;
i. New utility pole locations will be placed within approximately 10-20 feet in line of the
existing utility poles and will not require additional road right of way.
f. Future conditions which may be reasonably anticipated in the area in view of a normal course of
development
i. Future development and conditions which may be reasonably anticipated in the area
including roadway improvements have been coordinated with the Oro Valley Engineering
Division.
g. The type of terrain
i. Terrain and vegetation impacts for the Project will be considered during construction and
mitigated to the extent possible.
h. The practicality and feasibility of underground installation of such poles and wires with due regard
for the comparative costs between underground and above ground installations (provided,
however, that a mere showing that an underground installation shall cost more than an above
ground installation shall not, in itself, necessarily require issuance of a permit).
i. The option to underground transmission lines of 138 kilovolt capacity has significant
additional cost compared to overhead installations, approximately 3:1. In addition, the
heat that can be generated by 138 kilovolt transmission lines does not easily dissipate if
installed underground and can shorten the life span of crucial equipment required to
transmit safe and reliable electric service.
L in the event such poles and wires are for the sole purpose of carrying electricity or power or for
transmitting of telephone, telegraph, or television communication through or beyond the Town's
boundaries or from one (1) major facility to another, the practicality of feasibility of alternative or
other routes shall also be considered.
i. The option to reroute the existing transmission line would require a major undertaking to
include: new land right acquisition, new engineering design and construction, and
compliance with applicable zoning codes and ordinances. The additional cost associated
with re-routing the line would greatly exceed the cost for the proposed upgrade.
Thank you for your consideration and do not hesitate to contact me with any questions or concerns. I can be reached
at (520) 396-2767 or at isaline@tep.com
Respectfully,
Jason Saline, Environmental and Land Use Planner
Tucson Electric Power
TEP
Tucson Electric Power
Land Resources — RC131
3950 E. Irvington Road
Tucson, Arizona 85714-2114
138 Kilovolt Tangerine Road Transmission Line Upgrade
Project Description
Tucson Electric Power (TEP) is planning to make necessary upgrades to a segment of an existing 138 kilovolt (kV)
transmission line that connects TEP's North Loop Substation, located near West Tangerine Road and Interstate 10,
to the Rancho Vistoso Substation, located near East Tangerine Road and North Copper Mountain Drive. TEP must
complete these improvements to continue providing safe, reliable service to customers in the area. A portion of this
work will occur in Oro Valley within a 3.5-mile stretch of TEP's easement along the southern edge of Tangerine Road
between North Shannon Road and Copper Mountain Drive.
The Rancho Vistoso Substation is the primary power distribution source in the in this fast-growing area. Recent
projections indicate the transmission line is at risk of being overloaded in 2018 during times of peak energy demand,
exceeding North American Electric Reliability Corporation standards and shortening the lifespan of crucial
equipment. TEP must install higher -capacity conductor to increase the maximum operating temperature. The total
number of conductors will remain the same.
To accommodate the heavier, more resilient conductor, TEP will replace 32 wooden and steel poles with 32 self -
weathering steel monopoles. The current poles have an above ground height ranging between 51-68 feet will be
replaced by new poles with an above ground height range of 56-79 feet. The increased height is necessary to conform
with National Electric Safety Code standards and to support the upgraded conductor and additional load capacity.
TEP has applied for a Conditional Use Permit as required under the Town of Oro Valley zoning code; chapter 25 Use
Regulations, B. Requirements for Specific Non -Residential Uses, Sec. 22 New Utility Poles and Wires and Sec. 22.5
Use Permits.
Thank you for your consideration and do not hesitate to contact me with any questions or concerns. I can be reached
at (520) 396-2767 or at isaline@tep.com
Respectfully,
Jason Saline, Environmental and Land Use Planner
Tucson Electric Power
Y........................
Tucson Electric Power
138 Kilovolt Tangerine Road
Transmission Line Upgrade
Fact Sheet
Tucson Electric Power (TEP) is planning to
upgrade a segment of an existing 138 kilovolt
(kV) transmission line that connects TEP's North
Loop Substation, located near West Tangerine
Road and Interstate 10, to the Rancho Vistoso
Substation, located near East Tangerine Road
and North Copper Mountain Drive.
TEP must complete these improvements to
satisfy national safety code standards and to
continue providing safe, reliable service to
customers in the Oro Valley area. These
improvements also will accommodate
anticipated future growth in the area.
A portion of this work will be performed in Oro
Valley along the southern edge of Tangerine
Road between North Shannon Road and Copper
Mountain Drive. The Rancho Vistoso Substation
is the primary power distribution source in the
in this fast-growing area. Recent projections
indicate the transmission line is at risk of being
overloaded in 2018 during times of peak energy
demand, exceeding national standards and
shortening the lifespan of crucial equipment!
This steel monopole is representative of the
new equipment that TEP plans to install along
Tangerine Road.
TEP must install more resilient, higher -capacity
wires and replace 32 wooden and steel poles.
New steel poles with heights of 56-79 feet will
replace existing structures with heights of 51-68
feet.
For More Information:
Jason Saline
Environmental and Land Use Planner
(520) 396-2767 or jsaline@tep.com
West Boundary: Tangerine and Shannon Roads, located east East Boundary: Tangerine and Copper Mountain Roads,
of North Thornydale Road. located west of North 111 Avenue.
r i MOY m
rEP
Tucson Electric Power
Electric and Magnetic Fields
Electric and magnetic fields (EMFs) are part of our
everyday environment. They are emitted by power
lines and other electrically -powered systems that light,
cool and heat our homes, provide our communications
and entertainment and support other aspects of our
modern lifestyle. EMFs also are produced naturally
by the Earth.
For more than 30 years, scientists and researchers
from universities, national laboratories, health
agencies, the World Health Organization and other
groups have conducted research activities into possible
health effects of EMFs. According to this large body of
research, there are no confirmed health risks caused
by exposure to low-level EMFs.
What are EMFs?
The term "EMF" describes two invisible forces that
surround any electrical device. Both types of fields
weaken significantly as they extend further away
from the source.
Electric fields are produced by voltage — the strength or
'pressure' with which an electric current flows. Electric
fields can be weakened by solid objects such as
vegetation, buildings or other structures. The strength
of electric fields varies depending on the voltage of the
power line.
Magnetic fields are produced by current — the
movement of electrons through a conductor.
The EMFs associated with power lines and electrical
devices are much weaker than those associated with
other sources such as microwaves or radio waves;
they are considered to be "extremely low frequency"
fields at 60 Hertz (Hz). These EMFs, at the low end
of the electromagnetic spectrum, are described as
"non -ionizing" because they are not known to
damage DNA or cells directly.
Health Studies and Concerns
Although researchers and scientists have heavily
studied this issue since the 1970s, they have not
confirmed that any adverse health effects have been
caused by exposure to low-level EMFs.
• After a recent review of scientific literature about
the issue, the World Health Organization (WHO)
called for continued research but concluded that, "...
current evidence does not confirm the existence of
any health consequences from exposure to low level
electromagnetic fields."
• In 1997, a National Research Council committee
studying the issue concluded, "...the current body
of evidence does not show that exposure to these
fields presents a human -health hazard. Specifically,
no conclusive and consistent evidence shows that
exposures to residential electric and magnetic fields
produce cancer, adverse neurobehavioral effects, or
reproductive and developmental effects."
• Similarly, in 1999, the National Institute of
Environmental Health Sciences (NIEHS) reported
to the U.S. Congress that, "No consistent pattern
of biological effects from exposure to EMF had
emerged from laboratory studies with animals or
with cells."
• According to the National Cancer Institute: "No
consistent evidence for an association between any
source of non -ionizing EMF and cancer has been
found, despite numerous epidemiologic studies and
comprehensive reviews of scientific literature."
This research has been performed through
epidemiological, animal, biological and
clinical studies.
--
.Y...,o.... .........
Magnetic Field Exposure
Studies show that primary sources of EMF exposure
can be found at home or at work. Median magnetic
field strength, measured in milliGauss (mG), for
common household items is shown in the first
chart below.
Exposure levels vary considerably based on the
model of appliance, distance from it and its use. For
example, a hair dryer's "high" setting produces a
stronger magnetic field than its "low" setting. A dash
means the measurement could not be distinguished
from background measurements before the appliance
was turned on.
Dis ,nce rom source
6" 1' 2' 3'
. 11 Digital Clock 1 —CMIM
— —
® Electric Oven 9 4 — —
aji� Hair dryer 300 1 - -
!/// Microwave Oven 200 4 10 2
Refrigerator 2 2 1 —
Video Display Terminal (PCs with color monitors) 14 5 2 —
Washing Machine 20 7 1 —
Source: National Institute of Environmental Health Sciences
Magnetic fields surrounding everyday appliances can be stronger than fields near power lines, depending on
distance from the source. This chart shows typical magnetic field strengths of overhead power lines.
0'
33'
66'
98'
131'
500kV
81
72
51
33
21
230kV
38
28
15
8
5
138kV
33
22
11
5
3
69 kV
18
6
3
1
0
25 kV
10
5
2
1
0
Source: BC Hydro
TEP designs and builds its equipment to meet or exceed national building and safety standards.
Learn More
You can learn more about electric and magnetic fields by visiting these resources:
• World Health Organization: • Environmental Protection Agency:
www.who.int/peh-emf/en/ www3.epa.gov/radtown/electric-magnetic-
• U.S. National Institutes of Health, National fields.html
Institute of Environmental Health Sciences: www. • National Cancer Institute:
niehs.nih.gov/health/topics/agents/emf/ https://www.cancer.gov/
riep
Tucson Electric Power
• American Cancer Society:
www.Cancer.org/cancer/cancercauses/
rod iation-exposure/extremely-low-frequency-
radiation.html
For more information about our planned
infrastructure improvements, visit tep.com/projects.
Rev 1/18
North Loop -Rancho Vistoso
Reconductor
® Existing
J Existing/Replace
Existing Transmission Line
Jurisdictional Boundaries
= MARANA
ORO VALLEY
Data Sources:
TEP
Pima County GIS
Imagery: ESRI World Imagery
a soo 00o e
'Feat
II�
EP
Tucson Electric Power
This map is for planning purposes only.
TEP and UNS Energy make no warranty
of its accuracy.
r\MX Ds\0 ro_Valley_exh ibit_24x36. mxd