HomeMy WebLinkAboutPackets - 3-1-23 Meeting PresentationTown Council Meeting
Regular Session
March 1, 2023
Town Council Meeting
Announcements
Upcoming meetings
Meetings are subject to change. Check the Town website for meeting status.
Historic Preservation Commission
March 6 at 5 p.m.
Hopi Conference Room
Planning and Zoning Commission
March 7 at 6 p.m.
Council Chambers
Water Utility Commission
March 13 at 5 p.m.
Hopi Conference Room
Town Council Regular and Study Session
March 15 at 6 p.m.
Council Chambers
4
Town Council Meeting
Regular Session
March 1, 2023
6
Officers Katelyn Gomez, Michele Torres, Saul Diaz-Zuniga, and Clayton Haskins
7
8
Town Council Meeting
Regular Session
March 1, 2023
Community Center
Elevator Schematic Design Review
March 1, 2023
Community Center Elevator Update
At the November 16, 2022, meeting, Town Council directed staff to move
forward with design alternatives and to provide updated cost estimates for the
Limited Use Limited Application elevator (LULA) and a conventional elevator
that would work with exterior circulation options #2 and #5 presented that
evening.
For review, circulation options #2 and #5 are as follows:
Circulation Option #2 -The front entrance is accessed from existing handicap parking with a ramp that
leads to the existing building entrance at the middle (Golf Administration) level.
Circulation Option #5 -Lowering the front entrance/building facade to enter at the first floor and
connecting to new handicap parking spaces at the front of the building.
11
Exterior Circulation Option #2
Pros:
•Lower cost than any
solution that requires
building modifications.
Cons:
•Slightly more costly than
the current ramp option,
as it requires the
construction of a
completely new ramp.
•Has a long path of travel
from the existing
handicap parking spaces
and the elevation
difference is similar to the
existing ramp. Could be
considered a laborious
path of travel for building
patrons.
•Does not allow for the
creation of handicap
parking closer to the
entrance.12
Exterior Circulation Option #5
Pros:
•Provides the opportunity to
create new handicap
parking at the front
entrance.
•With the creation of this
new handicap parking
adjacent to the entrance
location, renders the least
path of travel length.
Cons:
•Most expensive exterior
circulation alternative as it
requires building
modification, Porto-
Cochere demolition and
parking lot grading to allow
patrons to enter at the first
floor.
13
Community Center Elevator Update
The designer has created a 3D representation of the existing building and virtually constructing both an elevator and LULA within the space constraints.
Schematic design has been completed.
Schematic design represents approximately a 30% level of a full construction document, and its purpose is to understand how all the constructed elements will ultimately work with one another. This design will also identify constraints and associated solutions, as well as how the cost of the project will be affected.
The schematic design package is divided into four options:
1.Conventional elevator and existing entrance (Circulation option #2)
2.Conventional elevator and lowered entrance (Circulation option #5)
3.LULA and existing entrance (Circulation option #2)
4.LULA and lowered entrance (Circulation option #5)
From these options, a more focused cost estimate has been compiled.
14
15
Option #1 -Elevator & Existing Entrance
Entrance and front of the building remain as is.
A new exterior ADA ramp will be constructed to access the existing building entrance.
The elevator is located near the entry and has three stops to access all three floor
levels.
The main stairs are slightly modified.
A new floor section is constructed for the upper floor level.
The elevator shaft will penetrate the roof.
The current construction cost estimate is $1.25M.
Option #1 -Elevator & Existing Entrance -Layout
16
Option #1 -Elevator & Existing Entrance -Elevation
17
Of note:
The elevator shaft
penetrates the
roof of the
building.
Architectural
treatment will be
required.
Roof joists will tie
into elevator shaft.
18
Option #2 -Elevator & Lowered Entrance
The building entrance and facade will be lowered to the lower floor level, providing
direct access.
ADA parking will be added to this area for direct access to the building entrance.
The elevator is located near the entry and has three stops to access all three floor levels.
Existing stairs will be relocated.
A new floor section is constructed for the upper floor level.
The elevator shaft will penetrate the roof.
The current construction cost estimate is $1.75M.
Option #2 -Elevator & Existing Entrance -Layout
19
Option #2 -Elevator & Existing Entrance -Elevation
20
Of note:
The elevator shaft
penetrates the
roof of the
building.
Architectural
treatment will be
required.
Roof joists will tie
into elevator shaft.
21
Option #3 -LULA & Existing Entrance
Entrance and front of the building remain as is.
A new exterior ADA ramp will be constructed to access the existing building entrance.
The LULA is located near the entry and has three stops to access all three floor levels.
The stairs to the lower level are slightly modified.
A new floor section is constructed for the upper floor level.
The current construction cost estimate is $750K.
Option #3 -LULA & Existing Entrance -Layout
22
Option #3 -LULA & Existing Entrance -Elevation
23
24
Option #4 -LULA & Lowered Entrance
The building entrance and facade will be lowered to the lower floor level, providing
direct access.
ADA parking will be added to this area for direct access to the building entrance.
The elevator is located near the entry and has three stops to access all three floor levels.
Existing stairs will be relocated.
A new floor section is constructed for the upper floor level.
The current construction cost estimate is $1.35M.
Option #4 -LULA & Lowered Entrance -Layout
Option #4 -LULA & Lowered Entrance -Elevation
Space Comparison of Elevator vs LULA
27ElevatorLULA
28
Recommendations
Staff understands from the last meeting that Council's preference is to install a
conventional elevator.
Since three of the four alternatives are expected to meet the budget and Council
preferred the elevator option, staff recommends that at least the two elevator options be
fully designed and bid as alternatives A and B.
The reasoning is that for both entrance configurations, the exterior design is not a large
component of the design costs.
The major portion of the design costs will be associated with the interior
architecture/engineering to install an elevator.
29
Schedule
Finish construction plans by July
Permitting and bidding in July
Award and construction starting in August
Expect a 6-to-9-month construction period –may be completed by February to
April 2024 –dependent on equipment availability
30
Questions?
Town Council Meeting
Regular Session
March 1, 2023