TOWN COUNCIL REPORT
DATE: November 15, 2016
TO: Mayor and Councilmembers
FROM: Daniel G. Sharp, Interim Town Manager
Stacey Lemos, Finance Director
SUBJECT: 1st Quarter CIP Status Report for FY 2016/17
As part of monitoring and communicating the status of the projects in the Town’s adopted
Capital Improvement Plan (CIP), staff has developed the attached Quarterly CIP Status Report
for the quarter ending September 30, 2016. This report lists all of the CIP projects approved in
the FY 2016/17 adopted budget along with fiscal year-to-date spending, the total project budget
and spending, and comments/notes for each project.
DISCUSSION
In the attached report, the Total Project column consists of the total project budget, which may
include prior year budget amounts plus the FY 2016/17 budget amount (if this project
commenced in a prior fiscal year and rolled over into the 2016/17 fiscal year). If the project is a
rollover project, the Actuals column includes amounts spent in the prior fiscal year plus amounts
spent in FY 2016/17.
The Fiscal Year 16/17 column consists only of the FY 2016/17 adopted budget amount for the
project, as well as actual amounts spent that fiscal year.
As a reminder, the CIP projects budgeted within the General Government CIP Fund are funded
with a General Fund transfer of one-time construction-related revenues and sales taxes
generated from residential and commercial construction activity occurring within the Town. This
report captures the most current, and up-to-date costs and status of the projects in the FY
2016/17 Capital Improvement Program through September 30, 2016.
RECOMMENDATION / CONCLUSION
This report is for information only.
Project NameActualsBudget% RemainingActuals Budget% RemainingStatus Comments/NotesGENERAL GOVERNMENT PROJECTSTransit Scheduling Software and Mobility Data System 1,527 90,000 98.3% 1,527 90,000 98.3%First phase of software has been installed with successful transfer of client data. Training on bookings and operations management started early September and will be completed by the end of October. Testing of the software and its elements continues with support from IT.Improvements at 680 Calle Concordia Facilities‐ 50,000 100.0%‐ 50,000 100.0%Construction has begun on the eight‐foot high masonry perimeter wall around the back half of the facilities. Staff anticipates that this project will be completed in January 2017.Two Additional Multi‐Use Fields at Naranja Park‐ 212,600 100.0%‐ 212,600 100.0%Initial work on this project will begin in May/June 2017. Construction will begin after July 4th, 2017, with the goal of project completion by winter 2017/2018. Replace Olympic Pool Heater at Aquatic Center‐ 148,000 100.0%‐ 148,000 100.0%Staff has worked with Lloyd Construction and the heater manufacturer to determine the best solution. Both entities have confirmed that the issue appears to be plumbing‐related, rather than heater‐related. Lloyd is scheduled to complete the plumbing work in October at no cost to the Town. Staff believes this will resolve the issue.El Conquistador Country Club & Golf Course Acquisition 350,000 350,000 0.0% 650,000 1,000,000 35.0% FY 16/17 is 2nd payment of 3‐year payment purchase plan.Property/ID and Southern Substation Building‐ 1,945,000 100.0% 516,890 2,475,000 79.1%Project design is underway. Construction may begin early 2017 (January‐March timeframe).Bond‐Funded Park Infrastructure‐ 5,000,000 100.0%‐ 5,000,000 100.0% Staff meeting in November to discuss options.TOTAL 351,527 7,795,600 95.5% 1,168,417 8,975,600 87.0%HIGHWAY FUND PROJECTSPavement Preservation Program 1,021 1,150,000 99.9% 1,021 1,150,000 99.9%Southern Arizona Paving was selected to perform the fall preservation treatments, which began September 9 and are scheduled to be completed mid‐November.QUARTERLY CIP STATUS REPORTFOR THE QUARTER ENDING SEPTEMBER 30, 2016TOTAL PROJECTFiscal Year 16/17Page 1 of 4F:\CIP\Quarterly Status Reports\FY 16‐17\Q1 FY 16‐17 CIP Status Report
Project NameActualsBudget% RemainingActuals Budget% RemainingStatus Comments/NotesQUARTERLY CIP STATUS REPORTFOR THE QUARTER ENDING SEPTEMBER 30, 2016TOTAL PROJECTFiscal Year 16/17Infrastructure Asset Management Software 1,147 50,000 97.7% 57,845 100,000 42.2%Project is proceeding and software upgrade Phase I was installed for the Cartegraph system. Work continues on support for transportation assets, including asphalt conditions, work orders and sign inventories. Go‐live was achieved late September 2016. The FY 16/17 rollover will be used for remaining phases, which will include vehicle maintenance, stormwater management and materials management. Tangerine Access to Safeway (1st Ave) ‐ Safety‐ 250,000 100.0% 36,439 286,439 87.3%Plans are at 100% and are with ADOT for right‐of‐way application. Currently exploring the option of taking over the Tangerine right‐of‐way from ADOT at Oracle to just past First Avenue. Side Cast Sweeper 63,973 85,000 24.7% 63,973 85,000 24.7% Equipment purchased; project complete. Skidsteer with Attachments and Level Best‐ 90,000 100.0%‐ 90,000 100.0% Equipment has been ordered. TOTAL 66,141 1,625,000 95.9% 159,278 1,711,439 90.7%COMMUNITY CENTER PROJECTSEnergy Efficiency Project‐ 3,000,000 100.0%‐ 3,000,000 100.0%The Town's energy contractor Trane is finalizing the energy audit for the Community Center. Scope of project may exclude solar panels at this time due to uncertainty of TEP rate case with the Arizona Corporation Commission. Golf Course Cart Path Improvements 47,909 50,000 4.2% 47,909 50,000 4.2% Project is complete. Tennis Court Improvements‐ 50,000 100.0%‐ 50,000 100.0%Currently resurfacing court 16 with in‐house staff. Courts 1 through 15 will be addressed in spring 2017.Elevator and New Entryway ‐ 331,000 100.0%‐ 331,000 100.0%Design is complete. Staff is awaiting completion of the Townwide ADA transition study before beginning construction.New Family/Teen Game Room ‐ 65,000 100.0%‐ 65,000 100.0% Staff is currently discussing project specifications.TOTAL 47,909 3,496,000 98.6% 47,909 3,496,000 98.6%LIBRARY IMPACT FEE FUND PROJECTSLibrary Parking Lot Enhancements 178,030 187,000 4.8% 201,520 210,490 4.3% Project is complete. TOTAL 178,030 187,000 4.8% 201,520 210,490 4.3%Page 2 of 4F:\CIP\Quarterly Status Reports\FY 16‐17\Q1 FY 16‐17 CIP Status Report
Project NameActualsBudget% RemainingActuals Budget% RemainingStatus Comments/NotesQUARTERLY CIP STATUS REPORTFOR THE QUARTER ENDING SEPTEMBER 30, 2016TOTAL PROJECTFiscal Year 16/17ROADWAY PROJECTSLambert Lane from La Cañada to Rancho Sonora 108,050 6,517,000 98.3% 842,250 7,251,200 88.4%Granite Construction Company was awarded the construction contract. Construction is scheduled to start early January 2017 and finish by October 2017. La Cañada Moore Intersection Study‐ 50,000 100.0%‐ 50,000 100.0%Staff is working with Parsons Brinkerhoff on scope of work. The study will begin before the end of 2016 and finish by July 2017. La Cañada Crosswalk Signals at Community Center‐ 250,000 100.0%‐ 250,000 100.0%Staff and the RTA are currently exploring the potential for a traffic signal, instead of crosswalk signals. Tangerine Road from La Cañada to Shannon‐ 2,710,000 100.0% 877 2,710,000 100.0%Utility relocation and easement acquisition are underway. Currently working on the joint utility trench from Twin Peaks Road to La Cañada Drive.La Cholla Boulevard from Overton to Tangerine 73,919 1,500,000 95.1% 783,226 2,209,307 64.5%Design is on‐going; data collection in progress. Design will be completed by summer 2017. Construction is expected to start by fall of 2017, funding permitting.TOTAL 181,969 11,027,000 98.3% 1,626,353 12,470,507 87.0%STORMWATER FUND PROJECTS4.5 Cubic Yard Wheel Loader (Lease Purchase) 47,345 50,000 5.3% 47,345 50,000 5.3% FY 16/17 is 3rd of 4‐year lease purchase plan.TOTAL 47,345 50,000 5.3% 47,345 50,000 5.3%WATER UTILITY PROJECTSWell E2 Upgrade 5,000 150,000 96.7% 5,000 150,000 96.7%Design is 20% complete and should be completed by February 2017. Construction expected in spring 2017. 24‐Inch Reclaimed Main Relocation Tangerine Road‐ 1,500,000 100.0% 591,561 2,091,561 71.7% Construction expected to be complete by January 2017.Add Reclaimed Booster Pump ‐ Thornydale Station‐ 200,000 100.0%‐ 200,000 100.0%Design is 100% complete. Notice to proceed with construction will be issued in November 2016. Relocate Three Pressure‐Reducing Valves 2,368 100,000 97.6% 2,368 100,000 97.6%Design is 20% complete and should be completed by January 2017. Construction will start February 2017. Production Facility Building Retrofit‐ 80,000 100.0%‐ 80,000 100.0%Design is 20% complete and should be completed by December 2016. Construction to follow. Dump Truck‐ 80,000 100.0%‐ 80,000 100.0% Vehicle has been ordered and is set to arrive in late October 2016. Page 3 of 4F:\CIP\Quarterly Status Reports\FY 16‐17\Q1 FY 16‐17 CIP Status Report
Project NameActualsBudget% RemainingActuals Budget% RemainingStatus Comments/NotesQUARTERLY CIP STATUS REPORTFOR THE QUARTER ENDING SEPTEMBER 30, 2016TOTAL PROJECTFiscal Year 16/17E‐C Pressure‐Sustaining Valve Naranja CAP Blending‐ 100,000 100.0%‐ 100,000 100.0%Design is 40% complete and should be completed by December 2016. Expect construction and project completion shortly thereafter. Replace Well Pumps‐ 75,000 100.0%‐ 75,000 100.0%Replacements will be identified throughout the fall of 2016. Project will be complete before June 2017. Main Valve Replacement Program‐ 50,000 100.0%‐ 50,000 100.0%No design dollars associated with this project. Project will be completed by June 2017. Glover Reservoir Lining‐ 100,000 100.0%‐ 100,000 100.0%Paint specifications are 90% complete. Target start date is January 2017. Will complete in FY 16/17.Big Wash Reservoir Coating‐ 100,000 100.0%‐ 100,000 100.0% Target start date is February 2017. Will complete in FY 16/17.Water Quality Control Program‐ 70,000 100.0%‐ 70,000 100.0%Materials and equipment have been ordered. In‐house installation will be completed by June 2017. Hydropneumatic (HP) Tank Replacement (Wells)‐ 60,000 100.0% 48,042 110,000 56.3% Tank has been ordered and should be installed by December 2016.West Lambert Lane 12‐Inch Main Relocation 2,696 600,000 99.6% 122,359 719,663 83.0% Design is 100% complete. Construction will begin January 2017. System Connection Upgrades‐ 50,000 100.0% 34,998 84,998 58.8%Construction should start in December 2016, and project should be completed in January 2017. La Cholla ‐ Lambert to Tangerine Main Relocation 19,372 70,000 72.3% 21,072 100,000 78.9%Design is 20% complete and should be completed by March 2017. Construction will occur in FY 17/18. TOTAL 29,436 3,385,000 99.1% 825,400 4,211,222 80.4%Page 4 of 4F:\CIP\Quarterly Status Reports\FY 16‐17\Q1 FY 16‐17 CIP Status Report