HomeMy WebLinkAboutInformational Records - Town Council Reports (5) Town Manager’s Office TOWN COUNCIL REPORT DATE: June 1, 2017 TO: Mayor and Councilmembers FROM: Daniel G. Sharp, Interim Town Manager Stacey Lemos, Finance Director SUBJECT: 3rd Quarter CIP Status Report for FY 2016/17 As part of monitoring and communicating the status of the projects in the Town’s adopted Capital Improvement Plan (CIP), staff has developed the attached Quarterly CIP Status Report for the quarter ending March 31, 2017. This report lists all of the CIP projects approved in the FY 2016/17 adopted budget along with fiscal year-to-date spending, the total project budget and spending, and comments/notes for each project. DISCUSSION In the attached report, the Total Project column consists of the total project budget, which may include prior year budget amounts plus the FY 2016/17 budget amount (if this project commenced in a prior fiscal year and rolled over into the 2016/17 fiscal year). If the project is a rollover project, the Actuals column includes amounts spent in the prior fiscal year plus amounts spent in FY 2016/17. The Fiscal Year 16/17 column consists only of the FY 2016/17 adopted budget amount for the project, as well as actual amounts spent that fiscal year. As a reminder, the CIP projects budgeted within the General Government CIP Fund are funded with a General Fund transfer of one-time construction-related revenues and sales taxes generated from residential and commercial construction activity occurring within the Town. This report captures the most current, and up-to-date costs and status of the projects in the FY 2016/17 Capital Improvement Program through March 31, 2017. RECOMMENDATION / CONCLUSION This report is for information only. Project NameActualsBudget% RemainingActuals Budget% RemainingStatus Comments/NotesGENERAL GOVERNMENT PROJECTSTransit Scheduling Software and Mobility Data System 77,950          90,000             13.4% 77,950          90,000              13.4%Software upgrade has been completed. Automatic customer notification is complete and on‐line. Final map upgrades are in process. Last phase of the project is a voucher‐less system, which will roll over into FY 17/18. Improvements at 680 Calle Concordia Facilities 44,695          50,000             10.6% 44,695          50,000              10.6%Construction is complete on the eight‐foot high masonry perimeter wall around the back half of the facilities. Two Additional Multi‐Use Fields at Naranja Park 4,269            212,600          98.0% 4,269            212,600            98.0%Initial work on this project will begin in May/June 2017. Heavy construction will begin after July 4th, 2017, with the goal of project completion by winter 2017/2018. Replace Olympic Pool Heater at Aquatic Center‐                     148,000          100.0%‐                     148,000            100.0%Staff worked with Lloyd Construction and the heater manufacturer to determine the best solution. Both entities confirmed that the issue appeared to be plumbing‐related, rather than heater‐related. Lloyd Construction has completed the plumbing work and the heater has been working at full capacity. Staff will continue to monitor the heater, but believe the replacement will not be necessary.El Conquistador Country Club & Golf Course Acquisition 350,000        350,000          0.0% 650,000       1,000,000        35.0% FY 16/17 is 2nd payment of 3‐year payment purchase plan.Property/ID and Southern Substation Building 110,736        1,945,000       94.3% 627,626       2,475,000        74.6%Plans are with Community Development & Public Works staff for final review. Project will roll over into FY 17/18. Bond‐Funded Park Infrastructure‐                     5,000,000       100.0%‐                     5,000,000        100.0%Project cost is estimated at $17M. Secondary property tax proposal to fund the project will be placed on the November ballot per Council direction on May 3, 2017.TOTAL 587,650      7,795,600     92.5% 1,404,540    8,975,600      84.4%QUARTERLY CIP STATUS REPORTFOR THE QUARTER ENDING MARCH 31, 2017TOTAL PROJECTFiscal Year 16/17Page 1 of 4F:\CIP\Quarterly Status Reports\FY 16‐17\Q3 FY 16‐17 CIP Status Report Project NameActualsBudget% RemainingActuals Budget% RemainingStatus Comments/NotesQUARTERLY CIP STATUS REPORTFOR THE QUARTER ENDING MARCH 31, 2017TOTAL PROJECTFiscal Year 16/17HIGHWAY FUND PROJECTSPavement Preservation Program 450,193        1,150,000       60.9% 450,193       1,150,000        60.9%Fall preservation project was completed. Spring project is currently in the bid award phase. Infrastructure Asset Management Software 21,754          50,000             56.5% 78,452          100,000            21.5%Fueling system upgrade and integration is the final component remaining on this project. Project will be completed within budget by end of current fiscal year. Tangerine Access to Safeway (1st Ave) ‐ Safety‐                     250,000          100.0% 36,439          286,439            87.3%Plans are at 100% and are with ADOT for right‐of‐way application. Council passed resolution on April 5, 2017 to take over the Tangerine right‐of‐way from ADOT at Oracle to just past First Avenue. Currently awaiting pavement treatment by ADOT and State Board action. Side Cast Sweeper 63,973          85,000             24.7% 63,973          85,000              24.7% Equipment purchased; project complete. Skidsteer with Attachments and Level Best 89,960          90,000             0.0% 89,960          90,000              0.0% Equipment purchased; project complete. TOTAL 625,880      1,625,000     61.5% 719,017      1,711,439      58.0%COMMUNITY CENTER PROJECTSEnergy Efficiency Project 419,595        3,000,000       86.0% 419,595       3,000,000        86.0%Golf course irrigation pump station has been replaced, pool system improvements are complete and water fixtures have been replaced. HVAC replacements and lighting retrofits will begin in late May 2017. Project will roll over into FY 17/18. Golf Course Cart Path Improvements 47,909          50,000             4.2% 47,909          50,000              4.2% Project is complete. Tennis Court Improvements 25,424          50,000             49.2% 25,424          50,000              49.2%Court 16 has been resurfaced with in‐house staff. Courts 1, 5, 6 and 7 were repainted in February. Courts 1 through 15 will be addressed further in August/September 2017.Elevator and New Entryway ‐                     331,000          100.0%‐                     331,000            100.0%Design is complete. Updated project cost estimate is $560K‐$660K. Project is on hold pending funding approval and completion of the Townwide ADA transition study.New Family/Teen Game Room ‐                     65,000             100.0%‐                     65,000              100.0% Project is on hold. TOTAL 492,928      3,496,000     85.9% 492,928      3,496,000      85.9%Page 2 of 4F:\CIP\Quarterly Status Reports\FY 16‐17\Q3 FY 16‐17 CIP Status Report Project NameActualsBudget% RemainingActuals Budget% RemainingStatus Comments/NotesQUARTERLY CIP STATUS REPORTFOR THE QUARTER ENDING MARCH 31, 2017TOTAL PROJECTFiscal Year 16/17LIBRARY IMPACT FEE FUND PROJECTSLibrary Parking Lot Enhancements 178,030        187,000          4.8% 201,520       210,490            4.3% Project is complete. TOTAL 178,030      187,000         4.8% 201,520      210,490          4.3%ROADWAY PROJECTSLambert Lane from La Cañada to Rancho Sonora 914,399        6,517,000       86.0% 1,648,599    7,251,200        77.3%Construction is underway. Substantial completion expected by October 2017.    La Cañada Moore Intersection Study‐                     50,000             100.0%‐                     50,000              100.0%Staff is working with Psomas on scope of work. The study is expected to be complete by August 2017.  Project will roll over into FY 17/18.La Cañada Crosswalk Signals at Community Center‐                     250,000          100.0%‐                     250,000            100.0%An intergovernmental agreement with the Regional Transportation Authority (RTA) for a traffic signal, as opposed to a crosswalk, was approved by Council and the RTA in January.  The cost estimate is approximately $500K. The project will rollover into FY 17/18 and is expected to start in September 2017.Tangerine Road from La Cañada to Shannon 1,162,775    2,710,000       57.1% 1,163,652    2,710,000        57.1%Utility relocation and easement acquisition are underway. Currently working on the joint utility trench from Twin Peaks Road to La Cañada Drive. La Cholla Boulevard from Overton to Tangerine 789,599        1,500,000       47.4% 1,498,906    2,209,307        32.2%Design is on‐going; data collection in progress. Open house was held in March. Design will be completed by summer 2017. Utility relocation construction is expected to start by fall of 2017. Acquisition processes have started. TOTAL 2,866,773  11,027,000   74.0% 4,311,157    12,470,507    65.4%STORMWATER FUND PROJECTS4.5 Cubic Yard Wheel Loader (Lease Purchase) 47,345          50,000             5.3% 47,345          50,000              5.3% FY 16/17 is 3rd of 4‐year lease purchase plan.TOTAL 47,345        50,000           5.3% 47,345        50,000            5.3%Page 3 of 4F:\CIP\Quarterly Status Reports\FY 16‐17\Q3 FY 16‐17 CIP Status Report Project NameActualsBudget% RemainingActuals Budget% RemainingStatus Comments/NotesQUARTERLY CIP STATUS REPORTFOR THE QUARTER ENDING MARCH 31, 2017TOTAL PROJECTFiscal Year 16/17WATER UTILITY PROJECTSWell E2 Upgrade 50,498          150,000          66.3% 50,498          150,000            66.3%Design is complete. Project scope has been expanded to incorporate additional improvements. Project construction will occur in FY 17/18.24‐Inch Reclaimed Main Relocation Tangerine Road 899,700        1,500,000       40.0% 1,491,261    2,091,561        28.7% Physical work complete; still processing remaining close‐out invoices.Add Reclaimed Booster Pump ‐ Thornydale Station 29,570          200,000          85.2% 29,570          200,000            85.2%Design is complete. Notice to proceed issued November 2016. Pump & materials are onsite. Project will be completed by end of current fiscal year.Relocate Three Pressure‐Reducing Valves 33,267          100,000          66.7% 33,267          100,000            66.7%Design is complete. Construction will be complete by end of current fiscal year.Production Facility Building Retrofit 13,266          80,000             83.4% 13,266          80,000              83.4%Design is complete. Project will begin in May 2017, with goal to complete by end of current fiscal year.Dump Truck 77,798          80,000             2.8% 77,798          80,000              2.8% Equipment purchased; project complete. E‐C Pressure‐Sustaining Valve Naranja CAP Blending 17,567          100,000          82.4% 17,567          100,000            82.4%Design is complete. Construction will be complete by end of current fiscal year. Replace Well Pumps‐                     75,000             100.0%‐                     75,000              100.0% Well pump D6 will be replaced by end of current fiscal year.Main Valve Replacement Program‐                     50,000             100.0%‐                     50,000              100.0%Identified valves to be replaced on Calle Loma Linda and project will be completed by end of current fiscal year. Glover Reservoir Lining 27,002          100,000          73.0% 27,002          100,000            73.0%Project began in March 2017, and is anticipated to be complete by end of April 2017.Big Wash Reservoir Coating‐                     100,000          100.0%‐                     100,000            100.0%Project will begin in April 2017, and will be completed by end of current fiscal year.Water Quality Control Program 37,800          70,000             46.0% 37,800          70,000              46.0%Materials and equipment have been received. In‐house installation will be completed by end of current fiscal year. Hydropneumatic (HP) Tank Replacement (Wells) 91,003          60,000              ‐51.7% 139,045       110,000             ‐26.4%Project complete. Project came in over budget due to unforeseen additional site improvements. This was covered by savings in other projects. West Lambert Lane 12‐Inch Main Relocation 10,225          600,000          98.3% 129,888       719,663            82.0%Construction began in March 2017; project expected to be complete by June 2017.System Connection Upgrades 41,901          50,000             16.2% 76,899          84,998              9.5% Project complete. La Cholla ‐ Lambert to Tangerine Main Relocation 68,587          70,000             2.0% 70,287          100,000            29.7% Design is 95% complete. Construction scheduled to start in FY 17/18. TOTAL 1,398,183  3,385,000     58.7% 2,194,147    4,211,222      47.9%Page 4 of 4F:\CIP\Quarterly Status Reports\FY 16‐17\Q3 FY 16‐17 CIP Status Report