HomeMy WebLinkAboutPackets - Council Packets (1871)Town Council Meeting
Regular Session
April 17, 2024
Town Council Meeting
Announcements
Upcoming meetings
Meetings are subject to change. Check the Town website for meeting status.
Stormwater Utility Commission
April 18 at 4:00 p.m.
Hopi Conference Room
Board of Adjustment –CANCELLED
April 23
Town Council Regular Session
May 1 at 6:00 p.m.
Council Chambers
4
OV’s Path Forward
Upcoming Community Events
Thursday, April 18
5:30 PM
Gaslight Music Hall
Thursday, April 25
3 PM – 5 PM
Starbucks
Friday, April 19
3 PM – 6 PM
Rosati’s Pizza
Friday, April 26
6 PM
Friday Night Concerts at Steam Pump
Tuesday, April 23
10 AM – 1 PM
Oro Valley Country Club
Saturday, April 27
9 AM – 11 AM
Savaya Coffee
5
Stay up -to -date about events & join the online conversation at
www.OVPathForward.com
Town Council Meeting
Regular Session
April 17, 2024
7
Spotlight on Youth – Isabelle Sparlin
Town Council Meeting
Regular Session
April 17, 2024
9
Mayor and Council Reports
Town Council Meeting
Regular Session
April 17, 2024
11
Town Manager’s Report
Town Council Meeting
Regular Session
April 17, 2024
13
Graduation of Youth Advisory Council (YAC) members
Jordan Adams
Undecided
Kennedy Blanchard
University of Arizona
Liam DaDeppo
George Washington University
Estelle Lee
Returning home to further
her education in Korea
Amiya Lotun
Stanford University
Patrick Luu
University of Arizona
Valerie Maynard
University of Arizona
Jaden Wu
Accepted to Johns Hopkins
Town Council Meeting
Regular Session
April 17, 2024
Vistoso Trails Nature Preserve Master Plan
What is a Master Plan?
Vision for the future
Long-Term Plan, covering 20-30 years
Not a detailed design
A conceptual framework for future development
Helps to establish policies
Top 3 Priorities from March 20, 2024 Study Session
Safety - $160K
Signage
Path Repairs – Broken, heaved, and heavily cracked
Obtaining quotes
Desert Garden – For example, up to $1M
Phased implementation if needed
Year 1-2 Project
Revegetation – Remaining funds
Revegetate as much as possible
Year 1-2 Project
Next Steps – If Council Approves Master Plan
Desert Garden Scope
Issue RFQ/RFP for the work
Select firm
Council workshop on Desert Garden
Revegetation
Hire Agronomist
Scope for RFP with recommended methodologies
Select firm
Celebrate the Preserve with the Community!
Project for: Town of Oro Valley
Project by: Sites Southwest
February 20, 2024
Vistoso Trails Nature Preserve
Master Plan – Final Approval
Town Council Session
April 17, 2024
Agenda
»Final Master Plan
»Costs and Phasing
»Q & A | Discussion
»Existing Cart Path becomes Preserve Trail (with
modifications)
»All Restrooms Rehabilitated
»Entire Preserve is Revegetated with Sonoran
Desert Native Plants
»Desert Garden Park at “Old Pond” with Ramadas
and viewing plaza.
»Four Parking Lots / Trailheads (one shared use)
Master Plan Highlights
Master Plan
Safety Improvements (cart path, signage…)
»Repaired and Rehabilitated Cart Path
»Safety Signage
»Reclamation
Infrastructure
»Parking Lots
»Trailheads
»Site Furnishings
»Repaired and Rehabilitated Cart Path
»Reclamation
Desert Garden
»Parking Lot
13 spaces with HC Parking
»Desert Native Plant Garden
Formal Landscape
Shade
Signage
Gravel Path through Garden (ADA)
»Viewing Plaza
Hardscape Plaza
Ramadas
Furniture
Revegetation
»Tees, Fairways, Greens, Sand Traps
»Driving Range
»Interstitial Spaces
Construction Costs: Safety Improvements
ITEM #ITEM DESCRIPTION UNIT QTY UNIT COST Total Notes
Safety Improvements Phase
1 Mobilization/Demobilization LS 1 $10,000.00 $10,000.00 Allowance
2 Construction Staking LS 1 $7,600.00 $7,600.00 Based on $1,700/AC
3 Selective Clearing, Pruning & Plant Relocation AC 2.9 $7,500.00 $21,750.00 Based on area
4 Cart Path Removals: broken, heaved, and heavily cracked LS 21 $420.00 $8,820.00 Adjusted at .75 of Build Cost
5 Cart Path Rebuilds: rebuild cart path in removal areas LS 21 $1,650.00 $34,650.00 Assuming 8'x16' ea @ $12/sf x 21 fixes = $1,536 ea
6 Safety Signage: share the path, cautionary, and yield signage LS 1 $2,700.00 $2,700.00 Based on $75.00 per sign
7 Earthwork - Unclassified Excavation, Including Placement and Compaction LS 1 $15,000.00 $15,000.00 Based on area not cubic yardage
Subtotal $100,520.00
Phase I Soft Costs Adjusted
Construction Contingency @ 25%$25,130.00
Design Fee @ 12%$15,078.00
Permits, Fees, Liability, Bonds, etc. (15%)$18,847.50
TOTAL $159,575.50
Notes for Safety Improvements
- Pond bulkhead removal and reseeding is included in pond area improvements estimate
- It is assumed that the SWPP is not necessary due to small amounts of land distrurbed
Construction Costs: Infrastructure
ITEM #ITEM DESCRIPTION UNIT QTY UNIT COST Total Notes
Infrastructure Phase (addtnl path improvements, parking, wayfinding, furnishing)
1 Mobilization/Demobilization LS 1 $20,000.00 $20,000.00 Allowance
2 Construction Staking LS 1 $30,000.00 $30,000.00 Based on $1,700/AC
3 Selective Clearing, Pruning & Plant Relocation LS 1 $10,000.00 $10,000.00 Allowance
4 Demolition LS 1 $10,000.00 $10,000.00 Allowance
5 Earthwork - Unclassified Excavation, Including Placement and Compaction LS 1 $50,000.00 $50,000.00 Allowance
6 Trailhead Parking at N Rancho Vistoso Blvd. (15 Spaces)LS 15 $5,000.00 $75,000.00 Based on CRC costs - per space $5000
7 ADA Trailhead Parking at W Vistoso Highlands Dr. ( 4 Spaces)LS 8 $5,000.00 $40,000.00 Based on CRC costs - per space $5000
8 Trailhead at W Vistoso Highlands Dr. LS 1 $30,000.00 $30,000.00
9 Cart Path Shoulder Improvements (4'-0" wide both sides)SF 215,520 $3.00 $646,560.00
10 Cart Path Drainage Improvements LS 1 $25,000.00 $25,000.00 Based on Phase 1 cost, increased by 50%
11 Site Furnishings (Benches, Bollards, Trash Receptacles)LS 1 $90,000.00 $90,000.00 Allowance
12 Reclamation (native seeding 2' edges of gravel paths on each side)SF 108,000 $0.22 $23,760.00
13 SWPP Plan Preparation, Installation, and Maintenance LS 1 $25,000.00 $25,000.00 Based on $1000/AC
14 Material Testing & Inspections LS 1 $15,000.00 $15,000.00 Allowance
Subtotal $1,090,320.00
Phase II Soft Costs Adjusted
Construction Contingency @ 25%$272,580.00
Design Fee @ 12%$163,548.00
Permits, Fees, Liability, Bonds, etc. (15%)$204,435.00
TOTAL $1,745,883.00
Notes for Infrastructure
- Parking at West Vistoso Highlands Dr is assumed to be the responsibility of the developer of the apartment project
- Parking at the Desert Garden at the Old Pond Area is included in that section of the cost estimate.
Construction Costs: Desert Garden
ITEM #ITEM DESCRIPTION UNIT QTY UNIT COST Total Notes
Desert Garden at Old Pond Area Phase
1 Mobilization/Demobilization LS 1 $15,000.00 $15,000.00 Allowance
2 Construction Staking LS 1 $10,090.00 $10,090.00 Based on $1,700/AC
3 Selective Clearing, Pruning & Plant Relocation LS 1 $5,000.00 $5,000.00 Allowance
4 Demolition of Bulkhead and Other Related Equipment LF 1,500 $15.00 $22,500.00 based on linear footage of bulkhead
6 Bermuda Removal and Off Site Disposal SF 148,670 $0.88 $130,829.60 fairways and greens
7 SWPP Plan Preparation, Installation, and Maintenance LS 1 $5,950.00 $5,950.00 Based on $1,000/AC
8 Reclamation (native seeding)SF 238,860 $0.22 $52,549.20 Based on $1,000/AC
9 Desert Garden Parking Lot (13 spaces and entry road) LS 13 $5,000.00 $65,000.00 Based on CRC costs per space
10 Earthwork - Unclassified Excavation, Including Placement and Compaction CY 11,750 $40.00 $470,000.00 6' depth by 105,415 SF
11 Flatwork - Plaza's and Other Concrete SF 12,790 $9.00 $115,110.00 based on $9.00 / SF
12 ADA Trail SF 3,680 $4.00 $14,720.00 area x $3.00/SF
13 Landscape Plantings and Irrigation SF 90,610 $3.00 $271,830.00
14 Material Testing & Inspections LS 1 $10,000.00 $10,000.00 Allowance
15 Ramadas and Shade Structures EA 3 $40,000.00 $120,000.00
Subtotal $1,308,578.80
Phase lll Soft Costs Adjusted
Construction Contingency @ 25%$327,144.70
Design Fee @ 12%$196,286.82
Permits, Fees, Liability, Bonds, etc. (15%)$245,358.53
TOTAL $2,077,368.85
Construction Costs: Driving Range
ITEM #ITEM DESCRIPTION UNIT QTY UNIT COST Total Notes
Driving Range Revegetation Phase
1 Mobilization/Demobilization LS 1 $30,000.00 $30,000.00 Allowance
2 Construction Staking LS 1 $10,000.00 $10,000.00 Lump Sum - simple project and paired down cost
3 SWPP Plan Preparation, Installation, and Maintenance LS 1 $10,000.00 $10,000.00 Based on $1,000/AC
4 Bermuda Removal and Off Site Disposal SF 435,600 $0.88 $383,328.00
5 Material Testing & Inspections LS 1 $5,000.00 $5,000.00 Allowance
6 ADA Trail (5'-0" Wide Compacted Fines)SF 12,650 $5.38 $68,057.00 Based on area
7 Reclamation (native seeding)SF 435,600 $0.22 $95,832.00 Based on $0.22/SF
Subtotal $602,217.00
Phase IV Soft Costs Adjusted
Construction Contingency @ 25%$150,554.25 Simple project therefore less contigency
Design Fee @ 2%$15,055.43 Simple project and therefore lesser fees
Permits, Fees, Liability, Bonds, etc. (15%)$112,915.69
TOTAL $880,742.36
Notes for Driving Range
- It is assumed for the Driving Range and other Hole Areas (tees, fairways, greens and traps) to be revegetated that the bermuda grass will be left in place and plowed under and not removed due to cost.
Construction Costs: Revegetation and
Reclamation (tees, fairways, greens, sand
traps
ITEM #ITEM DESCRIPTION UNIT QTY UNIT COST Total Notes
Hole Revegetation and Reclamation of Tees, Fairways, Greens and Sand Traps Phase
1 Tees, Fairway, Greens, Sand Traps (all holes except LS 1 $1,999,364.00 $1,999,364.00
2 Construction Staking LS 1 $30,000.00 $30,000.00 Based on $1,700/AC
2 Clear & Grub Old Sod, Disposal Fees AC 34.75 $4,356.00 $151,371.00 Based on $0.10/SF Estimate
3 SWPP Plan Preparation, Installation, and Maintenance AC 69.50 $1,000.00 $69,500.00 Based on $1,000/AC
Subtotal $2,250,235.00
Phase V Soft Costs Adjusted
Construction Contingency @ 10%$225,023.50
Design Fee @ 2%$49,505.17
Permits, Fees, Liability, Bonds, etc. (15%)$371,288.78
TOTAL $2,896,052.45
Notes for Tees, Fairways, Greens and Sand Traps
- It is assumed for the Hole Areas (tees, fairways, greens and traps) to be revegetated that the bermuda grass will be left in place and plowed under and not removed due to cost.
- See Per Hole Cost for Individual Hole Breakdowns
Allowance - (Rip, Seed, Straw & Compact) Based
on Hydroseed @ $0.62/SF
Construction Costs
ITEM DESCRIPTION UNIT QTY UNIT COST Total Notes
Phase V - Revegetation and Reclamation of Fairways, Greens and Tees
Hole 1: Tees, Fairway, Greens AC 3.28 $38,800.00 $127,264.00 Allowance - (Rip, Seed, Straw & Compact) Hydroseed @ $0.62/SF
Hole 2: Tees, Fairway, Greens AC 4.59 $38,800.00 $178,092.00 Allowance - (Rip, Seed, Straw & Compact) Hydroseed @ $0.62/SF
Hole 3: Tees, Fairway, Greens AC 1.05 $38,800.00 $40,740.00 Allowance - (Rip, Seed, Straw & Compact)Hydroseed @ $0.62/SF
Hole 4: Tees, Fairway, Greens AC 2.52 $38,800.00 $97,776.00 Allowance - (Rip, Seed, Straw & Compact)Hydroseed @ $0.62/SF
Hole 5: Tees, Fairway, Greens AC 3.39 $38,800.00 $131,532.00 Allowance - (Rip, Seed, Straw & Compact)Hydroseed @ $0.62/SF
Hole 6: Tees, Fairway, Greens AC 5.36 $38,800.00 $207,968.00 Allowance - (Rip, Seed, Straw & CompactHydroseed @ $0.62/SF
Hole 7: Tees, Fairway, Greens AC 1.5 $38,800.00 $58,200.00 Allowance - (Rip, Seed, Straw & Compact Hydroseed @ $0.62/SF
Hole 9: Tees, Fairway, Greens AC 3.09 $38,800.00 $119,892.00 Allowance - (Rip, Seed, Straw & Compact) Hydroseed @ $0.62/SF
Hole 10: Tees, Fairway, Greens AC 3.33 $38,800.00 $129,204.00 Allowance - (Rip, Seed, Straw & Compact) Hydroseed @ $0.62/SF
Hole 11: Tees, Fairway, Greens AC 3.37 $38,800.00 $130,756.00 Allowance - (Rip, Seed, Straw & Compact) Hydroseed @ $0.62/SF
Hole 12: Tees, Fairway, Greens AC 4.39 $38,800.00 $170,332.00 Allowance - (Rip, Seed, Straw & Compact) Hydroseed @ $0.62/SF
Hole 13: Tees, Fairway, Greens AC 0.92 $38,800.00 $35,696.00 Allowance - (Rip, Seed, Straw & Compact) Hydroseed @ $0.62/SF
Hole 14: Tees, Fairway, Greens AC 2.95 $38,800.00 $114,460.00 Allowance - (Rip, Seed, Straw & Compact)Hydroseed @ $0.62/SF
Hole 15: Tees, Fairway, Greens AC 1.15 $38,800.00 $44,620.00 Allowance - (Rip, Seed, Straw & Compact)Hydroseed @ $0.62/SF
Hole 16: Tees, Fairway, Greens AC 6 $38,800.00 $224,652.00 Allowance - (Rip, Seed, Straw & Compact)Hydroseed @ $0.62/SF
Hole 17: Tees, Fairway, Greens AC 0.79 $38,800.00 $30,652.00 Allowance - (Rip, Seed, Straw & Compact)Hydroseed @ $0.62/SF
Hole 18: Tees, Fairway, Greens AC 4.06 $38,800.00 $157,528.00 Allowance - (Rip, Seed, Straw & Compact)Hydroseed @ $0.62/SF
Subtotal $1,999,364.00
Phasing
Q & A | Discussion
Town Council Meeting
Regular Session
April 17, 2024
Steam Pump Ranch Shade Structure Project
History of the Shade Structure
Installed in 2012
Structure
Three custom wood structures with wood slat roofEach structure 12’ X 50’Installed end to end, with some spacing betweenElectric outlets on every other poleLightsMistersCloth covering attached for additional shade
Utilized BySaturday Heirloom Farmer’s MarketDay CampRentals