Fiscal Year 2018/2019
Financial Update Through June 2019
(Year-End, Unaudited)
September 18, 2019
Thank you Mayor and Council, I’m pleased to report that the Town’s finances continue to perform well and within budget through the month of April
5
General Fund
In the General Fund, total revenues collected this year through Apr are $32.5M compared to $32M collected last year through this month. We are about 83% of the way through the fiscal
year, and trending right in line with where we expect to be.
Expenditures through Apr total $31.1M compared to $28.4M spent last fiscal year through this month.
So through the month of April total collected revenues exceed expenditures by approx. $1.4M.
6
General Fund Highlights - Revenues
Local sales taxes exceeded budget by $1.6M, or 8.3%
License and permit revenues exceeded budget by $220K, or 10.3%
State-shared revenues exceeded budget by $170K, or 1.5%
Charges for services exceeded budget by $140K, or 5.8%
Interest income exceeded budget by $500K
Total revenues estimated to exceed budget by $2.3M, or 5.9%
A few highlights in the General Fund :
Local sales taxes are trending to end the year over budget by $564K, driven primarily by construction sales tax collections over the past few months.
Meanwhile, State shared revenues are trending right on budget at year-end
Overall, we are estimating to end the year with revenues coming in over budget by $560,000 or 1.4%
Gen Fund expenditures are estimated to come in under budget by about $2.3M, with about $600K due to personnel savings, $1M in estimated O&M savings, of which about $260K in savings is
due to the expiration of the OV Marketplace sales tax rebate ending as of December 31st. Additional savings of $550K is due to not making the subsidy transfer to the Highway Fund. And
remaining savings are being seen in areas across the budget such as utilities, fleet maintenance, and outside professional services.
As a result, the ending fund balance is estimated at $16.4M.
7
General Fund Highlights - Expenditures
Personnel savings of $680K, or 2.5%
Operations and maintenance savings of $990K, or 10.4%
Capital outlay savings of $180K, or 24.3%
$550K transfer to Highway Fund not necessary
Total expenditures estimated under budget by $2.4M, or 5.7%
Total revenues in the fund exceeded expenditures by $1.6M
Year-end fund balance estimated at $18.2M, or 46% of expenditures
A few highlights in the General Fund :
Local sales taxes are trending to end the year over budget by $564K, driven primarily by construction sales tax collections over the past few months.
Meanwhile, State shared revenues are trending right on budget at year-end
Overall, we are estimating to end the year with revenues coming in over budget by $560,000 or 1.4%
Gen Fund expenditures are estimated to come in under budget by about $2.3M, with about $600K due to personnel savings, $1M in estimated O&M savings, of which about $260K in savings is
due to the expiration of the OV Marketplace sales tax rebate ending as of December 31st. Additional savings of $550K is due to not making the subsidy transfer to the Highway Fund. And
remaining savings are being seen in areas across the budget such as utilities, fleet maintenance, and outside professional services.
As a result, the ending fund balance is estimated at $16.4M.
8
Highway Fund
In the Highway Fund, total revenues collected this year through Apr are $3.1M compared to $2.8M collected last year through this month. The total revenue budget is $4.1M.
Expenditures through Apr total $2.5M compared to $3M spent last fiscal year through this month. Total expenditure budget is $4.6M.
So through the month of April total collected revenues exceed expenditures by just over $600,000.
9
Highway Fund Highlights
HURF gas tax revenues exceeded budget by $270K, or 8.3%
Total revenues estimated under budget by $230K, or 5.6%
No subsidy transfer from General Fund
Total expenditures estimated under budget by $480K, or 10.4%
Year-end fund balance estimated at $694K
For Highway Fund highlights, HURF gas tax revenues are still trending over budget by $328K
Overall, revenues are estimated to come in under budget by $232K mainly due to the eliminated need for the General Fund subsidy transfer
Expenditures are estimated to come in under budget by $312K due primarily to the Tangerine Access to Safeway CIP project of $250,000 rolling over to next year’s budget.
Year –end fund balance is estimated at $523K
10
Community Center Fund
In the Community Center Fund, total revenues collected this year through Apr are $5.6M compared to $5.7M collected last year through this month. The total revenue budget is $6.7M.
Expenditures through Apr total $4.9M compared to $5.4M spent last fiscal year through this month. Total expenditure budget is $6.6M.
So through the month of April total collected revenues within the fund exceed expenditures by nearly $770K.
(savings – tennis, water, management fee)
11
Community Center Fund Highlights
Total revenues estimated to end year over budget by $90K, or 1.3%
Total expenditures estimated to end year under budget by $325K, or 4.9%
Total revenues in the fund exceeded expenditures by $502K
Year-end fund balance estimated at $312K
Restated beginning fund balance attributable to prior period adjustment of donation revenues
Overall, total revenues at year-end are estimated to come in about .6% or $39K underbudget
Total expenditures are estimated to end the year under budget by $295K
With a year-end fund balance in the fund of $273K
12
QUESTIONS?
13
14
Fiscal Year 2019/2020
Financial Update Through July 2019
September 18, 2019
Thank you Mayor and Council, I’m pleased to report that the Town’s finances continue to perform well and within budget through the month of April
15
General Fund
In the General Fund, total revenues collected this year through Apr are $32.5M compared to $32M collected last year through this month. We are about 83% of the way through the fiscal
year, and trending right in line with where we expect to be.
Expenditures through Apr total $31.1M compared to $28.4M spent last fiscal year through this month.
So through the month of April total collected revenues exceed expenditures by approx. $1.4M.
16
General Fund Highlights
All revenues estimated on budget at this time
Local sales tax collections total $1.6M, or 8.0% of budget
License and permit revenues total $343K, or 17.3% of budget
State-shared revenues total $947K, or 7.6% of budget
Charges for services revenues total $259K, or 10.1% of budget
Expenditures estimated to end year under budget by $114K due to personnel savings
Year-end fund balance estimated at $15.7M
A few highlights in the General Fund :
Local sales taxes are trending to end the year over budget by $564K, driven primarily by construction sales tax collections over the past few months.
Meanwhile, State shared revenues are trending right on budget at year-end
Overall, we are estimating to end the year with revenues coming in over budget by $560,000 or 1.4%
Gen Fund expenditures are estimated to come in under budget by about $2.3M, with about $600K due to personnel savings, $1M in estimated O&M savings, of which about $260K in savings is
due to the expiration of the OV Marketplace sales tax rebate ending as of December 31st. Additional savings of $550K is due to not making the subsidy transfer to the Highway Fund. And
remaining savings are being seen in areas across the budget such as utilities, fleet maintenance, and outside professional services.
As a result, the ending fund balance is estimated at $16.4M.
17
Highway Fund
In the Highway Fund, total revenues collected this year through Apr are $3.1M compared to $2.8M collected last year through this month. The total revenue budget is $4.1M.
Expenditures through Apr total $2.5M compared to $3M spent last fiscal year through this month. Total expenditure budget is $4.6M.
So through the month of April total collected revenues exceed expenditures by just over $600,000.
18
Highway Fund Highlights
HURF gas tax revenues expected to come in over budget by about $200K, due to one-time allocation approved in final state budget
Total revenues estimated to end year over budget by $227K
Expenditures estimated on budget at this time
Year-end fund balance estimated at $584K
For Highway Fund highlights, HURF gas tax revenues are still trending over budget by $328K
Overall, revenues are estimated to come in under budget by $232K mainly due to the eliminated need for the General Fund subsidy transfer
Expenditures are estimated to come in under budget by $312K due primarily to the Tangerine Access to Safeway CIP project of $250,000 rolling over to next year’s budget.
Year –end fund balance is estimated at $523K
19
Community Center Fund
In the Community Center Fund, total revenues collected this year through Apr are $5.6M compared to $5.7M collected last year through this month. The total revenue budget is $6.7M.
Expenditures through Apr total $4.9M compared to $5.4M spent last fiscal year through this month. Total expenditure budget is $6.6M.
So through the month of April total collected revenues within the fund exceed expenditures by nearly $770K.
(savings – tennis, water, management fee)
20
Community Center Fund Highlights
Revenues total $523K, or 7.8% of budget, and are estimated just over budget, by $24K or 0.4%
Expenditures total $624K, or 9.7% of budget, and are estimated just under budget, by $14K or 0.2%
Total revenues in the fund projected to exceed total expenditures by $335K
Year-end fund balance estimated at $647K
Overall, total revenues at year-end are estimated to come in about .6% or $39K underbudget
Total expenditures are estimated to end the year under budget by $295K
With a year-end fund balance in the fund of $273K
21
QUESTIONS?
22
23
Comprehensive Economic Development Strategy (CEDS)
Town Council
September 18, 2019
24
CEDS Plan
Justifies expanding economic development efforts
Builds on public input from Your Voice, Our Future General Plan
Provides current and projected situation analysis
Identifies key strategies and tactics
Creates framework to implement key ED goals from the General Plan and Strategic Leadership Plan
25
Overarching Goals
26
Initial Priorities
Retain, expand and attract primary employers
Retain and attract new retail
Develop an annexation blueprint
Improve Town responsiveness to Economic Development opportunities
Develop an integrated and dynamic community marketing strategy
27
Process
28
CEDS Updates
Condensed CEDS from 16 pages to 9 pages
Focused on key goals and actions
Removed analytical information
Tightened language
Aligned with suggestions from March 20th Study Session
29
CEDS Updates
Closely aligned with Town Council’s SLP
Goal 1A- Economic Vitality
Retain, expand and attract primary employers
Goal 1B- Attract Investment
Invest in retail and commercial centers
Complete targeted retail study
Facilitate industry specific presentations to clients and prospects
Goal 1C- Develop Comprehensive Annexation Blueprint
30
Summary and Recommendation
CEDS Plan
Expands five-year economic development strategy to:
Retain, expand and attract employers, retail, talent and investment
Enable job growth
Aligned with the Strategic Leadership Plan and provides the framework for implementing key ED goals
Recommend adoption of five year CEDS
31
32
Proposed Rezoning and
Two Conditional Use Permits for a
Self-Storage and Business Center
Northwest corner of Calle Concordia and Oracle Road
Town Council
September 18, 2019
33
Good evening…
Purpose
Applicant’s requests for a proposed self-storage and business center
A. Rezoning from large-lot residential (R1-144) to Tech-Park (T-P)
B. Conditional Use Permit to allow a building size over 15,000 square feet
C. Conditional Use Permit to allow a self-storage use
Planning and Zoning Commission recommended conditional approval of all three items
Oracle Road
Calle Concordia
Our purpose here tonight is to consider…
- What is a CSP?
- Use the Zoning Code (Design Principles and Standards) – subdivision design, connectivity, compatibility
PAD Development Standards
34
Future
Moore
Road
Palisades
South
Oracle Road
Linda Vista Blvd.
Oracle Road
Calle Concordia
Shadow Mountain Estates
James D. Kriegh
Park
OV Aquatic Center
Canyon Del Oro Baptist Church
Future Tech Park
300’
35
A. Rezoning Request
Large-lot residential (R1-144) to Technological Park
Review Tools
Your Voice, Our Future General Plan
Zoning Code Analysis
Development standards
Compatibility
Environmental standards
Existing Zoning
R1-144 (3.3 acre residential lots)
R1-144
R1-36
Private
School
and Church
36
A. Alignment with the General Plan
Commerce/Office Park
Areas where commercial, office and/or light manufacturing is appropriate
Business-park environment
Mix of light industrial, professional office, office/showroom, office/warehouse, retail services and related uses
Tier I Growth Area
Envisioned entire area as one, larger and cohesive Tech-Park campus
37
A. Tentative Development Plan
Self-Storage and Business Center
115,086 sf including basement
Up to 1,000 storage spaces, a business center and 13 Executive Office Suites
Building Height
Allowed: 34’
Proposed: 16’ max (1st floor); 25’ max (2nd floor)
Building Placement
Regulated by the Oracle Road Scenic Corridor (ORSCOD)
Proximity to OV Aquatic Center
Critical wash on the southern portion of the site
Oracle Road
Calle Concordia
150’
100’
38
A. Tentative Development Plan
Oracle Road
Calle Concordia
300’
Compatibility
Conserves 48% open space
Provides a 300’ foot buffer from adjacent residences
Impact to views
Access and Circulation
Shared access drive from Oracle Road
Anticipates future connection to development north of the site
Loading Zones
Screened by existing and dense vegetation and wall
6’10” wall to screen from OV Aquatic Center
39
B. Increased Building Size
Conditional Use Permit to allow a 115,086 sf building
Aligns with rezoning Tentative Development Plan
Any permitted use in Tech-Park zoning could occupy the space
Light manufacturing
Office or communication studios
Government, religious institutions and public schools
Professional offices
Technical services
Recreation facilities
Architectural design key aspect of review
40
B. Technological Park Architectural Design
41
B. Architectural Design
View facing Oracle Road
View facing Aquatic Center
View facing future Tech Park
View facing residences (300’ buffer)
42
B. Architectural Design
Colors and materials
More industrial as permitted
Desert and natural hues
Screen wall with landscaping
6’10” for moving vehicles
Designed to match building
Sets theme for future tech-park development
Colors and materials
Design elements such as a flat roof
Elements to reduce massing
43
C. Self-Storage Use
Conditional Use Permit to allow a self-storage use
Review criteria focuses on compatibility to adjacent uses
44
C. Impact on Tech-Park Uses
Self-storage is consistent with other Tech-Park uses (I.E. warehousing)
Larger buildings are common in Tech-Park areas
Foothills Business Park
Self-Storage
Religious institution
Office
Light Manufacturing
Foothills Business Park
45
C. Employment Space in T-P
Town initiated code amendment to increase Tech-Park (employment) space
Allow low-impact Tech-Park uses in Commercial zones
Request includes 5,414 sf of office space
Rental office
Business center
13 executive office suites
46
All requests reviewed for conformance with the General Plan
General Plan Conformance
Guiding Principle and Policies
Principle: Grow the number of high quality employment opportunities, including research/tech parks, light industry and profession office complexes
Policy SD.4: Protect and conserve healthy native vegetation during the development review process
Policy LU.5: Provide diverse land uses that meet the Town's overall needs and effectively transition in scale and density adjacent to neighborhoods.
Policy E.4: Support the Oro Valley workforce and residents through education and training programs and needed services and amenities.
47
Public Participation
One neighborhood meeting held in June 2018
Key Concerns
View impacts from the OV Aquatic Center and adjacent residences
Hours of operation (lighting and safety)
Permanent protection of open space area
Mitigation Measures
Varied building height
Placement of building
Restricted hours, onsite manager and surveillance
Recorded conservation easement
View from residences
View from Oracle
View parking lot
48
Planning and Zoning Commission
Meeting held on May 7, 2019 with the following key concerns:
Architectural design
Job creation and employment in Tech Park space
Impact of self-storage on the future Tech Park development to the north
Reconsidered on August 6, 2019 to address a technical discrepancy. Applicant revised requests to include the following:
Provided more faux windows to most visible sides
Added 13 executive offices suites and parking spaces to accommodate
49
Summary and Key Factors
Aligned with General Plan land use designation and vision for entire area
Transitional Land Use:
Low impact use between larger lot residential and future tech-park
Building placement and lower building heights
Added value as a Tech-Park Use:
Self-storage is consistent with Tech-Park uses
Does not deter other Tech-Park uses
Sets foundation for future tech-park development to the north
Concerns from residents were minimal and mitigated
Calle Concordia
Future Tech Park
Linda Vista Blvd.
Oracle Rd.
50
Recommendation
All items are in conformance with the Your Voice, Our Future General Plan and Zoning Code
Planning and Zoning Commission recommended conditional approval of all items, subject to the conditions in Attachment 1, Attachment 2 and Attachment 3.
Requires 3 separate motions
Item A (rezoning request) and Item B (CUP for larger building size) must be aligned
Natural Open Space
Significant Wash
Proposed
Building
51
New State Law and Testimony to Town Council
Calle
Concordia
Oracle Rd.
300’
52
53
Oro valley self-storage & Business center
Mayor & council meeting
September 18, 2019
54
Storage Facilities are Utilized for both Personal AND Business Use!
Home and Office Space Savings
Less expensive to lease smaller space and pay for offsite storage
Storage of equipment & supplies during offseason
Empty nesters looking to downsize, but keep their family possessions
Millennials with expensive belongings
Construction Industry
Commonly use mobile trailers that aren’t always permitted
Mobile trailers cost more and require additional delivery fees
Storage units are more secure with 24-hour surveillance and onsite manager
Restaurants and Catering
Most restaurant space devoted to the dining area to maximize profits
Storage needed for large appliances, tables and chairs for events
Caterers typically only have commercial kitchen space to keep overhead costs down, need space for supplies
General Commercial Use
Storing business files, legal paperwork and other documents takes up a lot of space
Retailers with stores and online-only sales need extra storage space for display models, additional inventory and trade show booth supplies
Safety, Security and Convenience
Secure, climate-controlled storage units keep items safe from theft or damage
Long access hours and loading dock are ideal for startups and those that regularly need to retrieve items
With starting a business comes the need for space, but many businesses and startups do not have the budget for large leased space with room for inventory and supplies in addition to
their employees. Therefore, when thinking about how much space is needed, self-storage is a cost-effective way of making the most of a company’s space budget.
55
55
Foothills Business Park
Compatible uses creating a successful T-P zoned campus
Sigma Technologies
Two pharmaceutical providers, medical providers and medical support companies
Automotive parts supplier
Freeport-McMoRan Copper & Gold
Traditional self-storage facility
Small businesses and space for startups
Foothills Business Park is similar in size to OVSS&BC and future T-P land up to Linda Vista
Foothills Business Park 32 AC
Arizona Self Storage 5 AC
vs.
OVSS&BC & neighboring T-P property 42± AC
OVSS&BC 5.7 AC (less than half developable)
56
Oracle Road
Honeywell
Aerospace
5 AC
Traditional
Self-Storage
Facility
Sigma
Technologies
Int’l, LLC
Foothills Business Park
Approximately 32 AC
56
Total Site Area is 5.69 AC
Buildable Area Limited to 2.25 AC
61.5% of total site will remain natural or revegetated
Net site area is too small, not what Primary Employers are looking for
57
Developable Area
Site and regulatory constraints limit developable area to 2.25 AC
50’ Building
Setback
45’ Building Setback
Critical Resource Area
(5% Max Disturbance)
150’ Setback
(ORSCOD)
2.25 acres remaining
57
58
Logistics Sought by Primary Employers
Most primary tech. employers need logistics:
Major Interstate Highway
Airport
Rail Infrastructure
Warehousing and Distribution
Small-scale logistics are needed to support existing businesses & FUTURE employers
that will be located on the property to the north.
Logistic alternatives
are needed to support existing businesses
& FUTURE employers
that will be located on the property to the north.
Oro Valley’s lack of air, rail & interstate logistics challenges its potential to attract
certain tech users
Creates a need for logistic alternatives
58
Executive Suites
Dynamic office spaces for 2-3 tenants each
25-30 Tenants
Small, affordable office space for startups
Virtual Office & Business Center
Flexible space can accommodate 10-15 “Solopreneurs”
40 to 50 NEW Jobs
Incuding at least 5 self-storage/business center positions
59
Project Goal
Increase total employment opportunities by providing additional office space and needed storage for a wide range of residents and businesses
59
PRIMARY EMPLOYER
10 ACRES
60
Draft Comprehensive Economic Development Strategy (CEDS) 2018-2023
1 ACRE
150 New Jobs
15 New Jobs
ORO VALLEY SELF-STORAGE & BUSINESS CENTER
40-50 New Jobs
2.25 ACRES (Net)
OVER 22 JOBS PER ACRE
60
Movable internal walls
No costly removal of tenant improvements
Convenient storage space for incubators and other small businesses
Easy conversion of unit sizes to adapt to shifts in space needs as companies grow
61
Tentative Development Plan
Building can be easily converted into additional office space
Loading Areas
Cross Access
Undisturbed Open Space Set Aside as Conservation Easement
100’ CCV Buffer
(Undisturbed Open Space)
Proposed Building
ORACLE ROAD (PUBLIC ROW)
CALLE CONCORDIA (PUBLIC ROW)
Trail
61
Less traffic than traditional office development
More diverse economic base
Not a big loss if company relocates
Relocations often mean companies are successful and outgrowing their space
Catalyst for Tech Park growth to the north
Conference rooms and other virtual office resources open to anyone in the community
Millennials and Baby Boomers make up over 50% of Oro Valley’s population
“By 2020, 40% of millennials will work from home.”
Business center and virtual office space is perfect for startups, entrepreneurs, consultants, retirees seeking smaller office space with low overhead
Flexible space that can be expanded to meet growing needs
Benefits of Virtual Office Space and “Solopreneurs”/Freelancers
62
Draft CEDS: “Identify opportunities to facilitate the creation of co-working space to help accommodate the emerging independent workforce.”
62
$1.8MM
30 Executive Office Tenants
15 Freelancers using Virtual Office Space
19% at $90,000 = $769,500
12% at $125,000 = $675,000
5% at $175,000 = $393,750
+
Sales tax revenue from consumer spending
$13MM
Construction price tag with a half million dollars in construction sales tax directly to Oro Valley
+
Future rental tax from 900-1,000 storage units could also provide sizable annual revenue to the Town
63
Economic Impact
1
Projected annual income for Freelancers per Draft CEDS Game Plan 2018-2023
63
64
Town of Oro Valley Major Employers
4,316 employees, TOV Website - June 2018
Technology
Roche
Honeywell Aerospace
Securaplane
Medical
Oro Valley Hospital
Casa de la Luz Hospice
Splendido
Business
Simpleview
Hilton El Conquistador
Education
Amphitheater School District
Civic
Town of Oro Valley
Existing diversity of employment base
Need for dynamic office space that can accommodate a variety of business professionals and industry types
64
Transitional use
Quiet, low intensity
Low amount of traffic generated from self-storage
Minimal parking required = more preservation
Asked how to ensure southern open space could remain undisturbed in perpetuity
Conservation easement to be dedicated to the Town or a local environmental organization (developer also willing to donate land)
Beautiful building screened from view on all sides, particularly from the OV Aquatic Center
Potential for job creation | Catalyst for new tech employment north to Linda Vista
65
Neighborhood Feedback
Project well-received at first neighborhood meeting, second mandatory meeting not required
65
66
Summary
Project promotes:
Local job growth and retention
Diverse economic base
T-P (Tech Park) expansion
High-quality development
Vegetation and view preservation
Helps fulfill Oro Valley’s need for self-storage
Meets the well-underserved need for self-storage in the community (4.9sf/person in OV vs. 8sf/person, which is equilibrium)
100% AC high-tech climate-controlled self-storage appealing to large and small businesses, startups, Solopreneurs and residents
Catalyst for T-P development to the north
Business center and executive suites component ideal for Solopreneurs and startups, fulfulls General Plan goals and policies of growing employement opportunities and supporting a diverse
economy
Movable internal walls allow building to be easily converted into additional office space
Diversity of office tenants working differing hours → reduces typical AM/PM peak hour office traffic and doesn’t compete with morning and afternoon school traffic
Transitional use:
Quiet
Ample open space
Low traffic
Blends into site with beautiful architecture
resembles an office building
large setbacks with vegetative screening
66