HomeMy WebLinkAboutPackets - Water Utillity Commission (68)
AGENDA
WATER UTILITY COMMISSION
REGULAR SESSION
May 12, 2025
HOPI CONFERENCE ROOM
11000 N. LA CAÑADA DRIVE
REGULAR SESSION AT OR AFTER 5:00 PM
CALL TO ORDER
ROLL CALL
CALL TO AUDIENCE - at this time, any member of the public is allowed to address the Commission on any
issue not listed on today’s agenda. Pursuant to the Arizona open meeting law, individual Commission
members may ask Town staff to review the matter, ask that the matter be placed on a future agenda, or
respond to criticism made by speakers. However, the Commission may not discuss or take legal action on
matters raised during "Call to Audience." In order to speak during "Call to Audience", please specify what
you wish to discuss when completing the blue speaker card.
REGULAR SESSION AGENDA
1.REVIEW AND APPROVAL OF THE MARCH 10, 2025 REGULAR SESSION MEETING MINUTES
2.UPDATE AND DISCUSSION ON THE APRIL WATER UTILITY COMMISSION FIELD TRIP (P.
ABRAHAM)
3.UPDATE AND DISCUSSION ON WATER UTILITY FINANCIALS (M. RALLIS)
4.UPDATE AND DISCUSSION ON WATER OPERATIONS (D. ALLRED)
5.UPDATE AND DISCUSSION ON WATER CONSERVATION PROGRAM (D. MANCE)
6.UPDATE AND DISCUSSION CAPITAL IMPROVEMENT PROJECTS (L. JACOBS)
7.UPDATE AND DISCUSSION ON WATER RESOURCE USAGE (P. ABRAHAM)
8.DISCUSSION AND POSSIBLE ACTION ON CANCELLATION OF JUNE AND JULY WATER UTILITY
COMMISSION REGULAR SESSIONS FOR SUMMER BREAK
9.TOWN COUNCIL MEETINGS/COMMUNICATIONS (COUNCILMEMBER MURPHY)
10.DIRECTOR'S REPORT (P. ABRAHAM)
CALL TO AUDIENCE - at this time, any member of the public is allowed to address the Commission on any issue
not listed on today’s agenda. Pursuant to the Arizona open meeting law, individual Commission members may ask
Town staff to review the matter, ask that the matter be placed on a future agenda, or respond to criticism made by
speakers. However, the Commission may not discuss or take legal action on matters raised during "Call to
Audience." In order to speak during "Call to Audience", please specify what you wish to discuss when completing
the blue speaker card.
ADJOURNMENT
POSTED: 5/8/25 at 5:00 p.m. by sa
When possible, a packet of agenda materials as listed above is available for public inspection at least 24 hours prior
to the Commission meeting in the Town Clerk's Office between the hours of 8:00 a.m. – 5:00 p.m.
The Town of Oro Valley complies with the Americans with Disabilities Act (ADA). If any person with a disability needs
any type of accommodation, please notify the Town Clerk’s Office at least five days prior to the Commission meeting
at 229-4700.
INSTRUCTIONS TO SPEAKERS
Members of the public have the right to speak during any posted public hearing. However, those items not
listed as a public hearing are for consideration and action by the Commission during the course of their
business meeting. Members of the public may be allowed to speak on these topics at the discretion of the
Chair.
If you wish to address the Commission on any item(s) on this agenda, please complete a blue speaker card located
on the Agenda table at the back of the room and give it to the Recording Secretary. Please indicate on the
speaker card which item number and topic you wish to speak on, or if you wish to speak during “Call to
Audience,” please specify what you wish to discuss when completing the blue speaker card.
Please step forward to the podium when the Chair announces the item(s) on the agenda which you are interested in
addressing.
1. For the record, please state your name and whether or not you are a Town resident.
2. Speak only on the issue currently being discussed by the Commission. Please organize your speech, you will only
be allowed to address the Commission once regarding the topic being discussed.
3. Please limit your comments to 3 minutes.
4. During “Call to Audience”, you may address the Commission on any issue you wish.
5. Any member of the public speaking must speak in a courteous and respectful manner to those present.
Thank you for your cooperation.
“Notice of Possible Quorum of the Oro Valley Town Council, Boards, Commissions and Committees: In accordance
with Chapter 3, Title 38, Arizona Revised Statutes and Section 2-4-4 of the Oro Valley Town Code, a majority of the
Town Council, Board of Adjustment, Historic Preservation Commission, Parks and Recreation Advisory Board,
Stormwater Utility Commission, and Water Utility Commission may attend the above referenced meeting as a
member of the audience only.”
Water Utility Commission 1.
Meeting Date:05/12/2025
Submitted By:Maritza Valenzuela, Water
SUBJECT:
REVIEW AND APPROVAL OF THE MARCH 10, 2025 REGULAR SESSION MEETING MINUTES
RECOMMENDATION:
N/A
EXECUTIVE SUMMARY:
N/A
BACKGROUND OR DETAILED INFORMATION:
N/A
FISCAL IMPACT:
N/A
SUGGESTED MOTION:
I MOVE to approve (approve with changes) the March 10, 2025 regular session meeting minutes
Attachments
3-10-25 DRAFT MINUTES
D R A F T
MINUTES
WATER UTILITY COMMISSION
REGULAR SESSION
March 10, 2025
HOPI CONFERENCE ROOM
11000 N. LA CAÑADA DRIVE
REGULAR SESSION AT OR AFTER 5:00 PM
CALL TO ORDER
Chair Niranjan Vescio called the regular session meeting to order at 5:00 p.m.
ROLL CALL
Present: Niranjan Vescio, Chair
David Atler, Commissioner
Alan Forrest, Commissioner
Greg Hitt, Commissioner
Joe Hornat, Commissioner
Michael Smejkal, Commissioner
Absent: Tom Marek, Vice Chair
Staff Present:Peter A. Abraham, Water Utility Director
Mary Rallis, Water Utility Administrator
Attendees: Mary Murphy, Town Councilmeber
CALL TO AUDIENCE - at this time, any member of the public is allowed to address the Commission on
any issue not listed on today’s agenda. Pursuant to the Arizona open meeting law, individual
Commission members may ask Town staff to review the matter, ask that the matter be placed on a future
agenda, or respond to criticism made by speakers. However, the Commission may not discuss or take
legal action on matters raised during "Call to Audience." In order to speak during "Call to Audience",
please specify what you wish to discuss when completing the blue speaker card.
No public speakers.
REGULAR SESSION AGENDA
1.REVIEW AND APPROVAL OF THE FEBRUARY 10, 2025 REGULAR SESSION MEETING MINUTES
Motion by Commissioner Alan Forrest, seconded by Commissioner Greg Hitt to approve the January
and Feburary meeting minutes
Vote: 4 - 0 Carried
3/10/25 Water Utility Commission Regular Session Meeting Minutes 1
Other: Commissioner David Atler (ABSTAINING)
Commissioner Joe Hornat (ABSTAINING)
2.UPDATE, DISCUSSION AND ACTION ON WATER UTILITY ANNUAL REPORT (P. ABRAHAM)
Water Utility Director Peter Abraham provided an update on the progress of the 2025 Water Utility
Annual Report, and asked if the Commission had any further comments. Discussion ensued amongst
the Commission and Water Utility Director Peter Abraham.
3.UPDATE AND DISCUSSION ON THE NWRRDS (P. ABRAHAM)
Water Utility Director Peter Abraham provided the following updates regarding the Northwest
Recharge, Recovery and Delivery System (NWRRDS) Project:
Foundation of the project
50-year IGA between Town of Oro Valley, Metro Water, and Town of Marana
NWRRDS partnered and independent projects
CMAR Method of project delivery with Borderland Construction
Slated for completion in July 2026
Updates on the partnered portion
Updates on the independent portion
Water Utility Director Peter Abraham provided an explanation between the different types of delivery
systems (Design-Bid-Build, Design-Build, Contractor Manager At Risk).
Discussion ensued amonsgt the Commission and Water Utility Director Peter Abraham regarding the
updates on the Northwest Recharge, Recovery and Delivery System project.
Discussion ensued amongst the Commission and Water Utility Director Peter Abraham regarding the
WIFA loan considering the current circumstances with the Federal Government.
Water Utiltiy Director Peter Abraham recongized Commissioner Alan Forrest and the previous Town of
Oro Valley Water Utility Directors for the efforts and hard work wiht the deparmtent.
4.TOWN COUNCIL MEETINGS/COMMUNICATIONS (COUNCILMEMBER MURPHY)
Town Councilmember Mary Murphy provided the following updates:
Firefighters held a charity BBQ and Councilmember Murphy, alongside previous Sheriff Mark
Napier were judges
Preliminary 5 year forecast through FY 29/30 was presented and is online to view
Water Rates increase passed unanimously
Golder Ranch and town of Oro Valley have partnered in hosting a wildlife fire Q&A on 3/14/25
5.DIRECTOR'S REPORT (P. ABRAHAM)
Water Utility Director Peter Abraham provided the following updates:
Schedule of upcoming Town Council meetings and Water Utility Commission meetings
Upcoming Water Utiltiy Commission field trip (Date TBD)
Upper Colorado Basin snowpack comparisons
Colorado River System Reservoir Status
ADJOURNMENT
3/10/25 Water Utility Commission Regular Session Meeting Minutes 2
Motion by Commissioner Alan Forrest, seconded by Commissioner Michael Smejkal to adjourn the
meeting at 5:57 p.m.
Vote: 6 - 0 Carried
I hereby certify that the foregoing minutes are a true and correct copy of the minutes of the regular session of the
Town of Oro Valley Water Utility Commission of Oro Valley, Arizona held on the 10th day of March, 2025. I further
certify that the meeting was duly called and held and that a quorum was present.
Dated this _____ day of ____________________, 2025.
___________________________
Maritza M. Valenzuela
Senior Office Specialist
3/10/25 Water Utility Commission Regular Session Meeting Minutes 3
Water Utility Commission 2.
Meeting Date:05/12/2025
Submitted By:Maritza Valenzuela, Water
SUBJECT:
UPDATE AND DISCUSSION ON THE APRIL WATER UTILITY COMMISSION FIELD TRIP (P. ABRAHAM)
RECOMMENDATION:
N/A
EXECUTIVE SUMMARY:
N/A
BACKGROUND OR DETAILED INFORMATION:
N/A
FISCAL IMPACT:
N/A
SUGGESTED MOTION:
N/A
Attachments
ITEM 02- FIELD TRIP REVIEW
Presented by:
Peter A. Abraham, P.E.
Water Utility Commission Meeting
May 12, 2025
Oro Valley Water Utility
Update & Discussion on the April
Water Utility Commission Field Trip
Fieldtrip Recap Monday April 7, 2025
8:15 am – Report to Town Hall
8:30 am – Leave Town Hall
9:15 am – 9:45 am: Tour of SAVSARP Recharge Facilities
9:45 am – 10:15 am: Tour of SAVSARP Reservoir & Booster Station
10:14 am – 3:00 pm: Return adventure to Town Hall
Commission field trip of Tucson Water’s Southern Avra Valley Storage & Recovery Project
(SAVSARP)
Field Trip Recap
Oro Valley Water Utility “Yesterday” and
“Today”
• Tucson Water staff explain aquifer
recharge, storage and recovery concepts
• Oro Valley / Tucson Water IGA
• In 2024 Oro Valley delivered 3,500 AF of
CAP water to SAVSARP facility for recharge
In 2024 Oro Valley recovered and
delivered 2,600 AF of CAP water to
the Oro Valley service area
Unrecovered CAP water minus a 5% cut
to the aquifer and evaporation becomes
a Long-Term Storage Credit for Oro Valley
Tucson Water Presentation
Discussion
Water Utility Commission 3.
Meeting Date:05/12/2025
Submitted By:Maritza Valenzuela, Water
SUBJECT:
UPDATE AND DISCUSSION ON WATER UTILITY FINANCIALS (M. RALLIS)
RECOMMENDATION:
N/A
EXECUTIVE SUMMARY:
N/A
BACKGROUND OR DETAILED INFORMATION:
N/A
FISCAL IMPACT:
N/A
SUGGESTED MOTION:
N/A
Attachments
ITEM 03- FINANCIAL UPDATE
Water Utility Commission Meeting
May 12, 2025
Oro Valley Water Utility
Update & Discussion on Water
Utility Financials
Mary Rallis, C.P.A.
Water Utility Administrator
Financial Update – Fiscal Year 2024/25 - Revenues
REVENUES
Actuals
Through
04/30/2025
Budget Notes
Potable Water Sales $13,603,807 $16,617,000 Projected to meet budget.
Reclaimed Water
Sales $1,243,346 $1,383,000 Projected to exceed budget by $150K due to one full
year of Naranja Park operations.
Groundwater
Preservation Fees $2,162,552 $2,600,000 Projected to meet budget.
Service Fees $714,339 $824,000 Projected to meet budget.
TOTAL REVENUES $17,724,044 $21,424,000 Revenues are projected to slightly exceed budget at fiscal
year end.
Financial Update – Fiscal Year 2024/25 - Expenses
EXPENSES
Actuals
Through
04/30/25
Budget Notes
Personnel $2,889,645 $3,992,428 Projected to be below budget by $400K due to
vacancy savings.
Operations &
Maintenance $8,997,553 $11,915,730 Projected to meet budget.
Capital $213,757 $1,067,884
Projected to not meet budget by $600K due to
projects being carried forward to next fiscal
year.
Debt Service $3,391,568 $3,391,568 Debt service paid on 7/1/24.
TOTAL EXPENSES $15,492,523 $20,367,610 Expenses are projected to be below budget by $1M at
fiscal year end.
Customer Service Update – Through 04/30/25
FY 2023/24 Through 04/30/25
New meters installed 198 95
Customer base 21,498 21,593
Water Smart Registered Accounts 7,819 8,042
Customer Portal 10,941 12,666
Discussion
Water Utility Commission 4.
Meeting Date:05/12/2025
Submitted By:Maritza Valenzuela, Water
SUBJECT:
UPDATE AND DISCUSSION ON WATER OPERATIONS (D. ALLRED)
RECOMMENDATION:
N/A
EXECUTIVE SUMMARY:
N/A
BACKGROUND OR DETAILED INFORMATION:
N/A
FISCAL IMPACT:
N/A
SUGGESTED MOTION:
N/A
Attachments
ITEM 04- UPDATE AND DISCUSSION ON WATER OPERATIONS
David E. Allred
Water Operations Manager
Water Utility Commission
May 12, 2025
Oro Valley Water Utility
Update and Discussion on
Water Operations Activities
OVWU Water Operations
24 ADEQ certified operators are responsible for the O&M of the
OV & CS potable water service areas:
47 active sites (wells, reservoirs, booster stations & CAP wheeling stations)
375 miles of water mains
2,394 fire hydrants
8,605 valves
36 PRV stations
Over 21,000 metered service connections with AMI technology
149 water sampling stations
Operations is responsible for the reclaimed water system:
7 active sites (reservoir, booster, lake feeds, & park irrigation)
15 miles of reclaimed water main
OVWU Water Operations
Additional Core Functions:
Operate and monitor the SCADA system for potable and reclaimed systems
Manage AZ811 locate request
Complete customer service work order request (new meter installs, re-reads
customer inquiries and other request from CSC)
Maintain drinking water compliance sampling and reporting in accordance
with SDWA
Work closely with other OVWU groups (Engineering and Admin) and Town
Departments
Water Operations FY24-25 Projects
Reclaim Booster Rehab
R&R 4 vertical turbine booster pumps and motors-rehab booster pump cans
Notice to Proceed issued 12/23/2024 to Keller Electrical/OTC Industrial
Project to be completed by 06/15/2025
Project cost = $352,594
Project re-scheduled for FY25-26 due to supply delays
Water Operations FY24-25 Projects
Big View Booster-PLC and Shade Upgrade
Project is part of the OVWU PLC Upgrade Program
Upgrade the PLC and extend the shade cover
Notice to Proceed issued 12/23/2024 to Smyth Industries
Project to be completed by 06/30/2025
Project cost = $122,783
Water Operations FY24-25 Projects
PLC Panel Programming
Project is part of the OVWU PLC Upgrade Program
Contract to program new PLCs at Big View, WP-13 and WP-15
Notice to proceed issued 12/23/2024 to EMA
Project to be completed by 06/30/2025
Project cost = $64,641
Water Operations FY24-25 Projects
Well C-5 Discharge Pipe
Project to replace discharge pipe from well to reservoir
Well rehabilitated in July 2024
Notice to Proceed issued 12/06/2024 to Weber Water Resources
Project completed on time
Project cost = $33,670
OVWU Water Operations
Discussion
Water Utility Commission 5.
Meeting Date:05/12/2025
Submitted By:Maritza Valenzuela, Water
SUBJECT:
UPDATE AND DISCUSSION ON WATER CONSERVATION PROGRAM (D. MANCE)
RECOMMENDATION:
N/A
EXECUTIVE SUMMARY:
N/A
BACKGROUND OR DETAILED INFORMATION:
N/A
FISCAL IMPACT:
N/A
SUGGESTED MOTION:
N/A
Attachments
ITEM 05- UPDATE AND DISCUSSION ON WATER CONSERVATION
Dan Mance
Water Conservation Specialist
Water Utility Commission
May 12, 2025
Oro Valley Water Utility
Update and Discussion on
Water Conservation Program
WaterSmart – Xperience Live 2025
Interactive conference with industry professionals hosted by
VertexOne – WaterSmart Developer
Key presentations included the impact of technology on water
conservation, AMI integration and brainstorming sessions on
managing challenges customers face today
WaterSmart – Customer Interaction
WaterSmart Utilization
36% of SFR eligible accounts signed up for alerts
3,590 unique visitors to the WaterSmart portal in 2024
1,233 customer conversations completed in 2024
WaterSmart – Leak Detection
Leaks detected by WaterSmart
11,708 leak alerts sent out in 2024
Customers not signed up for leak alerts are contacted in-person
Water Conservation – University of Arizona - Project WET
The University of Arizona hosted Project WET for Amphitheater School
District 4th graders – James D. Kreigh Park
Promotes awareness, knowledge, and stewardship of water resources through
education. Project WET provides engaging, science-based educational
materials and programs for teachers, students, and communities to better
understand and manage water in a sustainable way
Water Conservation – University of Arizona - Project WET
Fun Hands-On Events
Watershed Workshop –Kids learn about how water interacts with the
environment
Water Cycle Workshop – The movement and constantly changing form of water
is emphasized
Water Conservation – University of Arizona - Project WET
Fun Hands-On Events
Sustainability – Kids take part in a water relay race, teaching them about water
waste and conservation
Groundwater – The kids learn about how water moves through Earth materials
Water Conservation – Water Audits
Water Audits are available at no cost for Oro Valley Water Utility
Customers
A Water Audit is a process that tracks how water is used in a home or business to
identify ways to reduce waste and improve efficiency
Customers can contact the Utility to request assistance with tracking water leaks
121 Audits conducted since September 2024
Water Conservation – Behind the Meter
Seasonal newsletter for Oro Valley Water customers
Provided by mail, email, and posted on OVWU website
Front page is an introductory message from the Water Utility Director
Second page is various water conservation messaging and helpful information
Water Conservation – Strategic Plan Implementation
HOA and Customer Outreach
Water Conservation is developing a series of presentations for HOAs and
residential customers, with a focus on reducing outdoor irrigation. Efforts also
continue to monitor unplanned water use through the WaterSmart program
and to encourage broader customer participation in the platform
Water Conservation
Discussion
Water Utility Commission 6.
Meeting Date:05/12/2025
Submitted By:Maritza Valenzuela, Water
SUBJECT:
UPDATE AND DISCUSSION CAPITAL IMPROVEMENT PROJECTS (L. JACOBS)
RECOMMENDATION:
N/A
EXECUTIVE SUMMARY:
N/A
BACKGROUND OR DETAILED INFORMATION:
N/A
FISCAL IMPACT:
N/A
SUGGESTED MOTION:
N/A
Attachments
ITEM 07- UPDATE AND DISCUSSION ON CIP PROJECTS
Oro Valley Water Utility
Update and Discussion on
Capital Improvement Projects
Lee Jacobs, P.E., C.P.M.
Engineering Division Manager
Water Utility Commission
May 12, 2025
New Well Equipping:
TEP Power to transformer is in – just outside perimeter wall
Civil is 100% complete – PDEQ requested additional source sample
Well equipping design complete – control panel design 100% with specifications
100% discharge line to connect to existing water system
Project anticipated to go to bid in second quarter of FY 24-25
Power line conduits installed with discharge line to system complete to well perimeter
Second set of new source sampling is completed for submittal to PDEQ for ATC
Project on temporary hold until NWRRDS is secured
La Posada/ Nakoma Sky Production
Well
New Well Equipping
Drill production well to 780 feet below surface 16” diameter casing
Supplement “D6” Zone water
Project anticipated to go to bid in third quarter of FY 2025-2026
ATC has been received from PDEQ
Well civil design, electrical design, instrumentation and control design is complete
Perimeter wall material is determined and structural is designing wall
Project on temporary hold until NWRRDS is secured
Steam Pump Production
Well
These are currently on hold until a priority tank is identified.
Reservoir Inspections in progress
Operations is anticipating interior inspection results at the end of
April
Countryside bypass was an in-house design to allow for wheeling station to fill reservoir in
the evening when demand is low.
this will help us reduce our well pumping for CS-1 and CS-2
Construction is expected to be complete by early May 2025
AOC will be submitted in mid to late May 2025 to PDEQ
Countryside Bypass to fill reservoir at CS-1
NWRRDS Independent Shannon Rd. Reservoir & Bstr.
Project Complete
NWRRDS Independent Transmission Main
Shannon Road Booster Station to Tangerine Road Water Main
Project is 100% complete and in service
Part of NWRRDS Independent Project
Contractor is approximately 60% complete with construction of two zone booster facility
“F” and “G” Zone discharge lines within facility have been extended
Pump can foundation work in progress with pump cans installed
Portion of the perimeter footer and wall is constructed
Generator pad and placed with generator and Control Building is 50% complete
La Canada Two Zone (“F” & “G”) Booster
ConstructionBooster Station Construction Underway
NWRRDS Partnered CMAR Project
Construction is progressing – approximately 75 percent of main installed
Construction clearing for partnered booster began late 2024 with reservoir constructed in March of 2025
Reservoir coatings expected to be complete by end of April 2025
NWRRDS Partnered CMAR Project
Construction is progressing – approximately 75 percent of main installed
Construction clearing for partnered booster began late 2024 with reservoir constructed in March of 2025
Reservoir coatings expected to be complete by end of April 2025
NWRRDS Independent Twin Peaks Booster Station
CMAR Delivery Method
Held our first scheduling meeting April 2025
Oro Valley is lead agency
Oro Valley will manage the construction of each Partners booster station
Oro Valley will be reimbursed for expenses associated with Partner work
Approximately 3600 LF of Transmission Main along with Boosters
Work slated to begin in July 2025 with 10-month construction period
Discussion
Water Utility Commission 7.
Meeting Date:05/12/2025
Submitted By:Maritza Valenzuela, Water
SUBJECT:
UPDATE AND DISCUSSION ON WATER RESOURCE USAGE (P. ABRAHAM)
RECOMMENDATION:
N/A
EXECUTIVE SUMMARY:
N/A
BACKGROUND OR DETAILED INFORMATION:
N/A
FISCAL IMPACT:
N/A
SUGGESTED MOTION:
N/A
Attachments
ITEM 06- WATER RESOURCE USAGE
Peter A. Abraham, P.E.
Water Utility Director
Water Utility Commission
May 12, 2025
Oro Valley Water Utility
Update & Discussion on
Water Resource Usage
Oro Valley Main Service Area January – March Water Use by Type
Countryside Service Area January – March Water Use by Type
Discussion
Discussion
Water Utility Commission 10.
Meeting Date:05/12/2025
Submitted By:Maritza Valenzuela, Water
SUBJECT:
DIRECTOR'S REPORT (P. ABRAHAM)
RECOMMENDATION:
N/A
EXECUTIVE SUMMARY:
N/A
BACKGROUND OR DETAILED INFORMATION:
N/A
FISCAL IMPACT:
N/A
SUGGESTED MOTION:
N/A
Attachments
ITEM 09- DIRECTOR'S REPORT
Peter A. Abraham, P.E.
Water Utility Director
Water Utility Commission Meeting
May 12, 2025
Oro Valley Water Utility
Director’s Report
Upcoming Meetings
May 21, 2025 Town Council Regular Session
Council Chambers @ 6 p.m.
June 4, 2025 Town Council Regular Session
Council Chambers @ 6 p.m.
(Public Hearing on Rates & Tentative Budget)
June 9, 2025 Water Utility Commission Meeting
Hopi Room @ 5 p.m. – Possible Cancellation
June 18, 2025 Town Council Regular Session
Council Chambers @ 6 p.m.
(Budget Adoption)
July 2, 2025 Town Council Summer Break
July 14, 2025 Water Utility Commission Meeting
Hopi Room @ 5 p.m. – Possible Cancellation
July 16, 2025 Town Council Summer Break
August 6, 2025 Town Council Summer Break
August 11, 2025 Water Utility Commission Meeting