HomeMy WebLinkAboutPackets - Water Utillity Commission (73)
AGENDA
WATER UTILITY COMMISSION
REGULAR SESSION
May 11, 2026
HOPI CONFERENCE ROOM
11000 N. LA CAÑADA DRIVE
REGULAR SESSION AT OR AFTER 5:00 PM
CALL TO ORDER
ROLL CALL
CALL TO AUDIENCE - at this time, any member of the public is allowed to address the Commission on any
issue not listed on today’s agenda. Pursuant to the Arizona open meeting law, individual Commission
members may ask Town staff to review the matter, ask that the matter be placed on a future agenda, or
respond to criticism made by speakers. However, the Commission may not discuss or take legal action on
matters raised during "Call to Audience." In order to speak during "Call to Audience", please specify what
you wish to discuss when completing the blue speaker card.
REGULAR SESSION AGENDA
1.REVIEW AND APPROVAL OF THE MARCH 9, 2026 REGULAR SESSION MEETING MINUTES
2. UPDATE AND DISCUSSION ON THE MAY WATER UTILITY COMMISSION FIELD TRIP (P.
ABRAHAM)
3.TOWN COUNCIL MEETINGS/COMMUNICATIONS (COUNCILMEMBER MURPHY)
4.UPDATE AND DISCUSSION ON CAPITAL IMPROVEMENT PROJECTS (L. JACOBS)
5.UPDATE AND DISCUSSION ON WATER CONSERVATION PROGRAM (D. MANCE)
6.UPDATE AND DISCUSSION ON WATER OPERATIONS (D. ALLRED)
7.UPDATE AND DISCUSSION ON WATER UTILITY FINANCIALS (M. RALLIS)
8.UPDATE AND DISCUSSION ON WATER RESOURCE USAGE (P. ABRAHAM)
9.DIRECTOR'S REPORT
10.DISCUSSION AND POSSIBLE ACTION ON CANCELLATION OF JUNE AND JULY WATER UTILITY
10.DISCUSSION AND POSSIBLE ACTION ON CANCELLATION OF JUNE AND JULY WATER UTILITY
COMMISSION REGULAR SESSIONS
CALL TO AUDIENCE - at this time, any member of the public is allowed to address the Commission on any issue
not listed on today’s agenda. Pursuant to the Arizona open meeting law, individual Commission members may ask
Town staff to review the matter, ask that the matter be placed on a future agenda, or respond to criticism made by
speakers. However, the Commission may not discuss or take legal action on matters raised during "Call to
Audience." In order to speak during "Call to Audience", please specify what you wish to discuss when completing
the blue speaker card.
ADJOURNMENT
POSTED: 5/6/2026 at 5:00 pm by ck
When possible, a packet of agenda materials as listed above is available for public inspection at least 24 hours
prior to the Commission meeting in the Town Clerk's Office between the hours of 8:00 a.m. – 5:00 p.m.
The Town of Oro Valley complies with the Americans with Disabilities Act (ADA). If any person with a disability
needs any type of accommodation, please notify the Town Clerk’s Office at least five days prior to the Commission
meeting at 229-4700.
INSTRUCTIONS TO SPEAKERS
Members of the public have the right to speak during any posted public hearing. However, those items not
listed as a public hearing are for consideration and action by the Commission during the course of their
business meeting. Members of the public may be allowed to speak on these topics at the discretion of the
Chair.
If you wish to address the Commission on any item(s) on this agenda, please complete a blue speaker card located
on the Agenda table at the back of the room and give it to the Recording Secretary. Please indicate on the
speaker card which item number and topic you wish to speak on, or if you wish to speak during “Call to
Audience,” please specify what you wish to discuss when completing the blue speaker card.
Please step forward to the podium when the Chair announces the item(s) on the agenda which you are interested
in addressing.
1. For the record, please state your name and whether or not you are a Town resident.
2. Speak only on the issue currently being discussed by the Commission. Please organize your speech, you will
only be allowed to address the Commission once regarding the topic being discussed.
3. Please limit your comments to 3 minutes.
4. During “Call to Audience”, you may address the Commission on any issue you wish.
5. Any member of the public speaking must speak in a courteous and respectful manner to those present.
Thank you for your cooperation.
“Notice of Possible Quorum of the Oro Valley Town Council, Boards, Commissions and Committees: In accordance
with Chapter 3, Title 38, Arizona Revised Statutes and Section 2-4-4 of the Oro Valley Town Code, a majority of the
Town Council, Board of Adjustment, Historic Preservation Commission, Parks and Recreation Advisory Board,
Stormwater Utility Commission, and Water Utility Commission may attend the above referenced meeting as a
member of the audience only.”
Water Utility Commission 1.
Meeting Date:05/11/2026
Submitted By:Meagan Ackerson, Water
SUBJECT:
REVIEW AND APPROVAL OF THE MARCH 9, 2026 REGULAR SESSION MEETING MINUTES
RECOMMENDATION:
Staff recommends approval.
EXECUTIVE SUMMARY:
N/A
BACKGROUND OR DETAILED INFORMATION:
N/A
FISCAL IMPACT:
N/A
SUGGESTED MOTION:
I MOVE to approve the March 9, 2026 regular session minutes.
Attachments
3-9-2026 draft minutes
D R A F T
MINUTES
WATER UTILITY COMMISSION
REGULAR SESSION
March 9, 2026
HOPI CONFERENCE ROOM
11000 N. LA CAÑADA DRIVE
REGULAR SESSION AT OR AFTER 5:00 PM
CALL TO ORDER
Chair Smejkel called the meeting to order at 5:00 p.m.
ROLL CALL
Present: Rebecca Badruddoja, Commissioner
Alan Forrest, Commissioner
Joe Hornat, Vice Chair
Steven Linder, Commissioner
Michael Smejkal, Chair
Niranjan Vescio, Commissioner
Absent: Greg Hitt, Commissioner
Staff Present: Peter A. Abraham, Water Utility Director
Lee Jacobs, Engineering Division Manager
Attendees: Councilmember Mary Murphy, Council Liaison
CALL TO AUDIENCE - at this time, any member of the public is allowed to address the Commission on any
issue not listed on today’s agenda. Pursuant to the Arizona open meeting law, individual Commission
members may ask Town staff to review the matter, ask that the matter be placed on a future agenda, or
respond to criticism made by speakers. However, the Commission may not discuss or take legal action on
matters raised during "Call to Audience." In order to speak during "Call to Audience", please specify what
you wish to discuss when completing the blue speaker card.
No public speakers
REGULAR SESSION AGENDA
1.REVIEW AND APPROVAL OF THE FEBRUARY 9, 2026 REGULAR SESSION MEETING MINUTES
Motion by Vice Chair Joe Hornat, seconded by Commissioner Niranjan Vescio to approve the February 9,
2026 regular session meeting minutes.
Vote: 6 - 0 Carried
3/9/26 Water Utility Commission Regular Session Meeting Minutes 1
2.TOWN COUNCIL MEETINGS/COMMUNICATIONS (COUNCILMEMBER MURPHY)
Councilmember Murphy provided the following updates:
Transportation Art By Youth (TABY) ribbon-cutting event
Naranja Multi-Use Path is still under construction
NWRRDS pipe-line is ~50% complete
Council approved the notice of intent to increase the potable water rates on 3/4/26
Issues with cell-phone reception North of Tangerine- Police is also trying to advocate for better
receptio
3.UPDATE, DISCUSSION AND ACTION ON WATER UTILITY ANNUAL REPORT (P. ABRAHAM)
Water Utility Director Peter A. Abraham thanked the Commission for their input and comments on the
2026 Water Utility Annual Report, as the comments are important.
Water Utility Director asked for final input on the 2026 Annual Report. Small changes that Maritza
Valenzuela will change. Any suggestions will be due by Friday, March 13, 2026.
Motion by Commissioner Niranjan Vescio, seconded by Vice Chair Joe Hornat to make a
recommendation to include minor revisions by March 13, 2026 to rendered to Council.
Vote: 6 - 0 Carried
4.UPDATE AND DISCUSSION ON THE NWRRDS (L. JACOBS)
Water Engineering Division Manager Lee Jacobs provided the following updates regarding the NWRRDS
projects:
In 2017, Metro Water, Marana and Oro Valley unanimously approved the NWRRDS IGA, a 50-year
IGA with Metro lead agency.
Is a significant project for Oro Valley and its neighboring cities.
Partnered Project Foundation:
Marana, Oro Valley & Metro Water
Capacity Entitlement
Cost share
CMAR Delivery method
History of the NWRRDS partnered project
Independent Project:
History of the independent project
4 transmission main projects
3 booster stations
All projects are slated for completion by February 2027
Discussion ensued among the Commission and Water Utility Staff Peter A. Abraham and Lee Jacobs
regarding both the partnered and independent NWRRDS projects.
5.UPDATE & DISCUSSION ON THE COLORADO RIVER (P. ABRAHAM)
Water Utility Director Peter A. Abraham provided the following updates regarding the Colorado River:
3/9/26 Water Utility Commission Regular Session Meeting Minutes 2
Water Utility Director Peter A. Abraham provided the following updates regarding the Colorado River:
Colorado River System
The current Drought Contingency Plan expires in October 2026
Colorado River is in the midst of a 26-year drought
Negotiated Agreement deadlines missed
Colorado River States missed critical 2/14/26 deadline
Federally Imposed Solutions in review
Discussion ensued among the Commission regarding the Colorado River updates.
6.DISCUSSION AND POSSIBLE ACTION REGARDING THE WATER UTILITY COMMISSION FIELD TRIP
IN APRIL (P. ABRAHAM)
Water Utility Director Peter A. Abraham provided the following information regarding the upcoming Water
Utility Commission upcoming field trip set to happen in April 2026:
Tentative dates
Schedule
Tour of NWRRDS Project (Partnered & Independent)
Peter A. Abraham asked Commissioners to send their availability to Maritza Valenzuela by Friday, March
13, 2026.
ADJOURNMENT
Motion by Vice Chair Joe Hornat, seconded by Commissioner Niranjan Vescio to adjourn the meeting at
6:34 p.m.
Vote: 6 - 0 Carried
I hereby certify that the foregoing minutes are a true and correct copy of the minutes of the regular session of the
Town of Oro Valley Water Utility Commission of Oro Valley, Arizona held on the ____ day of
____________________, 2026. I further certify that the meeting was duly called and held and that a quorum was
present.
Dated this _____ day of ____________________, 2026.
___________________________
Maritza M. Valenzuela
Senior Office Specialist
3/9/26 Water Utility Commission Regular Session Meeting Minutes 3
Water Utility Commission 2.
Meeting Date:05/11/2026
Submitted By:Meagan Ackerson, Water
SUBJECT:
UPDATE AND DISCUSSION ON THE MAY WATER UTILITY COMMISSION FIELD TRIP (P. ABRAHAM)
RECOMMENDATION:
n/a
EXECUTIVE SUMMARY:
n/a
BACKGROUND OR DETAILED INFORMATION:
n/a
FISCAL IMPACT:
n/a
SUGGESTED MOTION:
This item is for discussion only.
Attachments
Staff Presentation
Peter A. Abraham, P.E., Water Utility Director
Water Utility Commission Meeting
March 11, 2026
Oro Valley Water Utility
Update & Discussion on the
Water Utility Commission Fieldtrip
Fieldtrip Itinerary – NWRRDS
NWRRDS Fieldtrip – Partnered & Independent Projects
Major NWRRDS Components
NWRRDS Project – Partnered & Independent
2017 IGA
2019 - 2024Partnered Projects Designed(+/- $21M Total)OV Share
2019 - 2024Independent Projects Designed(+/-$31.7M Total)
Independent Projects
Partnered Projects
FY 25/26 (+/-$5.2M)Twin Peaks Bstr. Station
Project
Complete
(+/-$52.7M)
FY 22/23 ($.75M)GW Blending Main
FY 25/26 (+/-$14.5M)5 Mile Water main
FY 23/24 ($.95M)E-Zone @ Naranja
FY 20/21 (+/-$1M)Recovery Wells Drilled
FY 23/24 – 25/26 (+/-$20M)CMAR Project Delivery Method
FY 23/24 (+/-$5.5M)Shannon Rd. Res. & Bstr.
FY 23/24 – 24/25 (+/-$3.7M)La Canada Bstr. Stations
FY 24/25 (+/-$1.1M)E-Zone @ Tangerine
Pr
o
g
r
e
s
s
A
p
r
i
l
.
2
0
2
6
NWRRDS Fieldtrip
NWRRDS Fieldtrip group photo
NWRRDS photos
NWRRDS photos
Water Utility Commission 4.
Meeting Date:05/11/2026
Submitted By:Meagan Ackerson, Water
SUBJECT:
UPDATE AND DISCUSSION ON CAPITAL IMPROVEMENT PROJECTS (L. JACOBS)
RECOMMENDATION:
n/a
EXECUTIVE SUMMARY:
n/a
BACKGROUND OR DETAILED INFORMATION:
n/a
FISCAL IMPACT:
n/a
SUGGESTED MOTION:
Item is for update and discussion only
Attachments
CIP Update
Oro Valley Water Utility
Update and Discussion on
Capital Improvement Projects
Lee Jacobs, P.E., C.P.M.
Engineering Division Manager
Water Utility Commission
May 11, 2026
Hydraulic model to manage demands and expectations to service the WSA H1 (WP-15)and I1 (WP-14) are complete.
Operational Contingency plan –Reservoir isolation and removal from service early June 2026
Temporary relocatable reservoir is 100% complete in-place and ready to be disinfected and tested.
Reservoir Rehabilitation and Planning
Water Plant 14 (WP-14) Reservoir Rehabilitation
El Con short main design is completed and into PDEQ for Approval to Construct (ATC) 8 - inch interconnection at the tennis courts to El Conquistador Western Town.
We have now shared the proposed alignment with all the stake holders TOV Parks and Recreation, El Conquistador Management, and Golf Course Management we’ve been meeting to present to HOA, Resort ownership, TOV Parks and Recreation and Golf Management.
The redundant feed will allow us to work on other parts of the system and have assurances that we will be able to provide uninterrupted service. The interconnect provides a permanent solution to ensure redundancy and system reliability.
On current schedule is to begin construction in May 2026, in coordination with events scheduled at golf course and western town to ensure we don’t interrupt scheduled activities.
El Conquistador 8-inch Ductile Iron Pipe Interconnect
Operations discovered a line shaft failure on June 11, 2025
A contractor was brought in to remove motor and pump. Well D-9 was purged and video logged
Engineering took over on October 2, 2025, to work on equipping well with new pump and lowering pump.
Engineering calculated new parameters for pump, reviewed pump cuves and selected a new pump for this site and equipment has been installed and is operational.
Installation is now completed with pump running and water going into the system. Work was completed on April 21, 2026
Well D-9 Rehabilitation
Part of NWRRDS Independent Project to extend additional water resources into the F1 &
G1 WSA’s
Contractor is 100% complete with construction of two zone booster facility and control building
“F1” and “G1” Zone discharge lines within facility have been extended and connected
All Testing has been completed and OVWU has accepted all construction of site and is now operating as designed
La Canada two Zone (“F” & “G”) Booster Construction
Booster Station Construction Completed and Operational
NWRRDS Independent Transmission Main Project
Construction is now completed from Shannon Road Booster to Blue Bonnet – approximately 4.2 miles of 20-inch main
Currently completing mitigation of portions of right-of-way
Some minor punch list items such as, bollards to protect infrastructure and minor grading along alignment to ensure drainage flows remain the same.
NWRRDS Partnered Transmission Main Project
Construction is progressing – approximately 75 percent of main installed
Construction clearing for partnered booster began late 2024 with reservoir constructed in March of 2025
Reservoir coatings completed April 2025
Suction piping within the booster and forebay site is 90% complete
NWRRDS Partnered Reservoir and Booster Site at Twin Peaks and Lambert Lane
NWRRDS Partnered Reservoir and Booster Site at Twin Peaks and Lambert Lane
NWRRDS Independent Twin Peaks Booster Station
CMAR Delivery Method
Project General Conditions and Value Engineering Finalized October 2025, Long lead time items have been ordered and expected to be ready to install once construction has begun for those items.
Oro Valley is lead agency coordinating all activity between Marana, Metro Water and OVWU
Oro Valley will manage the construction of each Partners booster station, as well as lead on inspections
Oro Valley will be reimbursed for expenses associated with Partner work
Approximately 3600 LF of Transmission Main along with Three Boosters included with this portion of the project
Work slated to begin in early February 2026 with 12 months construction period expected.
Arizona Water Engineer of the Year 2026
Mike Sanders, P.E.
Oro Valley Water Engineering Division
•Mike’s greatest pride is his family. Wife
Mary, daughter and son-in-law Devin,
and my son Paul
•11 years with BOR-Tucson Field
Office...building the Central Arizona
Project (CAP Canel) from Brady Pump
Station East of Eloy, to Black
Mountain/ Snyder Hills Pump Stations
near Ajo Hwy and Kinney Road.
•26 years with COT-TW leading a design
team constructing and rehabilitating
water production facilities for Potable
and Reclaimed water systems.
•4 years with TOV Water Utility providing
project manamgement to OVWU;
MDWID; and Marana Water to
complete the Northwest Water
Recharge, Recovery & Delivery
System.
Question and Discussion
Water Utility Commission 5.
Meeting Date:05/11/2026
Submitted By:Meagan Ackerson, Water
SUBJECT:
UPDATE AND DISCUSSION ON WATER CONSERVATION PROGRAM (D. MANCE)
RECOMMENDATION:
n/a
EXECUTIVE SUMMARY:
n/a
BACKGROUND OR DETAILED INFORMATION:
n/a
FISCAL IMPACT:
n/a
SUGGESTED MOTION:
Item is for update and discussion only
Attachments
Staff Presentation
Update and Discussion on Water Conservation
Program
Water Utility Commission
May 11, 2026
Daniel Mance, Water Conservation Specialist
1
2
WaterSmart
Water Monitoring Capabilities
For the majority of 2025 customers relied on the water monitoring capabilities of WaterSmart to conserve water.
37% of SFR eligible accounts signed up for alerts
3,828 unique visitors to the WaterSmart Portal in 2025
1,392 customer conversations over the portal in 2025
9,841 leak alerts sent out in 2025
The most common explanation for leaks was Outdoor Watering System which accounted for 42% of leaks confirmed in 2025
3
SpryIDM – The Oro Valley Customer Portal for Water Use Monitoring
Water Monitoring Capabilities
SpryIDM was added in late 2025 to the Customer Portal to enhance the water monitoring capability and provide a more convenient solution for customers.
21,667 total eligible active accounts.
As of April 2026, there are 13,239 registered accounts on the Portal.
6,138 Unique Logins have been recorded since introduction.
4
Water Audits are available at no cost for Oro Valley Water Utility Customers
Water Audits
A Water Audit is a process that tracks how water is used in a home to identify ways to reduce waste and improve water conservation efficiency.
Customers can contact Water Conservation to request assistance with tracking water use and potential leaks.
184 Water Audits conducted in 2025.
5
Environmental Education Exchange (E3)
Outreach
Water Utility staff attended a learning session hosted by the Utility’s education consultant, E3.
The learning session was presented to a group of first grade students at Lehman Academy in Oro Valley.
Students were taught through interactive learning about water resources and conservation.
6
OVPD National Night Out
Water Conservation Outreach
October 24, 2025.
An informal outreach with local families on Water Conservation and environmental stewardship.
Over 100 families visited and received
materials on Water Conservation.
7
SaddleBrooke Philanthropic Educational Organization (PEO) Women’s Group
Outreach
Presented to the group on October 27, 2025.
Topics were informational on water resources and tips on water
conservation at the home.
Approximately 50 people attended
the session which included Oro
Valley and SaddleBrooke residents.
8
Oro Valley Community Academy Presentation
Outreach
October 30,2025.
Participated in the Oro Valley Community Academy.
The Community Academy is a fun and interactive opportunity for residents to learn about the Town
and local government.
The Water Conservation presentation focused on at
home water conservation ideas and local water resources.
9
Oro Valley State of the Town and Oro Valley Volunteer Ceremony
Outreach
October 30,2025.
Water Conservation had a booth at both the Oro Valley State of the Town and the Oro Valley Volunteer Ceremony.
Information and materials were available on water conservation for attendees.
10
Vistoso Village HOA
Outreach
February 17,2026.
A presentation was made to the Vistoso Village HOA on home water conservation.
Attendees were presented with information on local water resources and tips for water conservation.
Featured topics included WaterSmart and the new SpryIDM, conservation tips, and information on water audits
11
Sun City Vistoso Presentation
Outreach
March 31, 2026.
A presentation on home water conservation was conducted with a group of Sun City Vistoso residents.
Topics included information on local water resources and opportunities for Water Conservation at home and in gardens.
The presentation concluded with a lively Q&A session.
12
Future Presentations
Outreach
Our goal is to provide water conservation presentations to as many HOA’s as possible.
Help us get the word out!
Discussion
13
Water Utility Commission 6.
Meeting Date:05/11/2026
Submitted By:Meagan Ackerson, Water
SUBJECT:
UPDATE AND DISCUSSION ON WATER OPERATIONS (D. ALLRED)
RECOMMENDATION:
n/a
EXECUTIVE SUMMARY:
n/a
BACKGROUND OR DETAILED INFORMATION:
n/a
FISCAL IMPACT:
n/a
SUGGESTED MOTION:
Item is for update and discussion only
Attachments
Staff Presentation
David E. Allred
Water Operations Manager
Operator in Direct Responsible Charge
Water Utility Commission
May 11, 2026
Oro Valley Water Utility
Update and Discussion on Water Operations Activities
OVWU Water Operations
27 ADEQ certified operators are responsible for the O&M of the OV & CS potable water service areas:
Currently have 5 vacant positions
41 active sites (wells, reservoirs, booster stations & CAP wheeling stations)
375 miles of water mains
2,394 fire hydrants
8,605 valves
36 PRV stations
Over 21,000 metered service connections with AMI technology
149 water sampling stations
Operations is responsible for the reclaimed water system:
7 active sites (reservoir, booster, lake feeds, & park irrigation)
15 miles of reclaimed water main
OVWU Water Operations
Additional core functions:
Operate and monitor the SCADA system for potable and reclaimed systems
Manage AZ811 locate request
Complete customer service work order request (new meter installs, manual reads, customer inquiries and other request from CSC)
Maintain drinking water compliance sampling and reporting in accordance with the Safe Drinking Water Act (SDWA)
Work closely with other OVWU groups (engineering and admin) and Town departments
Water Operations Administration
Reclaimed Facility Booster Rehabilitation:
Booster station in service since 2004
Four pumps, motors, and discharge heads getting replaced with new equipment. Concrete pump cans getting video inspected
Project completed April 2026
Pumping capacity increased from ~850 GPM to 1350 GPM per pump
Water Operations Administration
Rural Water Association of Arizona 2026 Operator of the Year
Jeffrey A. Kane has dedicated more than 25
years to the water utility profession and public
service, including service as a Utilities Systems
Journeyman in the United States Air Force and
the Arizona Air National Guard
Mr. Kane holds a Master of Public Administration
from Arizona State University, a Master of
Business Administration, and a Bachelor of
Science in Business Administration. He has earned
the Certified Public Manager (CPM) credential
through Arizona State University, is a Lean Six
Sigma Green Belt, and maintains advanced State
of Arizona certifications in water distribution and
treatment, along with extensive federal
emergency management training
Water Production Activities
Well C-5 Repairs:
August 2025 – Oil tube unthreaded
Pump and equipment pulled to determine cause
7 swedge patches, and new pump installed
Returned to service April 2026
Water Production Activities
Well D-9 Repairs:
No pumping volume caused a low amperage shutdown
Equipment pulled and cause of failure was a broken coupling on the drive shaft
Two sonar-jet cleanings, brush and bail, and video scan completed
Project turned over to Water Engineering October 2025
Returned to service May 2026
Water Production Activities-ADC Inmate Work Program
Program Obstacles:
OVWU down to one day a week with 1 or 2 inmates
Limited to mostly landscape mitigation and maintenance around water facilities
Water Control Systems Activities
Programmable Logic Controller and Instrumentation Upgrades:
Project is needed to replace “legacy” remote instrumentation and PLCs
10-year CIP project.
Rancho Vistoso Booster Station-2024
Upgraded PLC and all instrumentation as part of booster rehab CIP project
Water Control Systems Activities
Big View Booster Station-2025
Moved up on list due to failing “legacy” PLC
Upgraded PLC and RTU cabinet
Added in Operator Interface Terminal (OIT)
Water Control Systems Activities
La Canada Reservoir and Booster Station-2025
Part of the NWRRDS system, two zone boosters added
New control building
Upgraded PLC with new RTU cabinet
Added in OIT
Added in reservoir hatch intrusion alarm
Water Control Systems Activities
Water Plant 13-2026
Staff built panel in 2025
Upgraded PLC with new RTU cabinet
Added in OIT
Added in reservoir hatch intrusion alarm
Water Control Systems Activities
Water Plant 15-2026
Staff built panel in 2025
Upgraded PLC with new RTU cabinet
Added in OIT
Added in reservoir hatch intrusion alarm
Added in two meters for water inlet and water outlet flows
Upgraded site intrusion system
Water Control Systems Activities
Well C-9-2026
Upgraded PLC with new RTU cabinet
Added in OIT
Added in future analyzer points
Water Control Systems Activities
Future panels 2026-2027
Well D-9 will be complete June 2026
Big Wash FY26-27, to be done in house by staff
Copper Creek Station FY26-27, staff will build panel and install
Deer Run Reservoir FY26-27, staff will build panel and install
Naranja Facility FY26-27, tentative depending on other sites
Water Distribution Activities
Distribution System Projects:
Partnership with OVWU Engineering and GRFD, installing two new fire hydrants
Linda Vista & Calle Concordia
Water Distribution Activities
Distribution System Projects:
In partnership with OVWU Engineering and GRFD, installing two new fire hydrants
Rancho Verde
Water Distribution Activities
Distribution System Projects:
OVCC – 2 days of potholing and locating the watermain for GPS tagging
Water Distribution Activities
Distribution System Projects:
WP-15 – Saddle Tap & Drill, Insertion Meters, Conduit Trech Preparation
Water Meter Operations Activities
Meter Maintenance:
Identifying meters manufactured 10 years and older for replacement
Goal is to replace 400-500 meters monthly
Pilot program with Kamstrup and Metron meters
Water Quality Activities
Water System Compliance
Staff monitors the Arizona Safe Drinking Water Information System (AZSDWIS) continuously to ensure that the water systems are in compliance with the
SDWA
Water Quality Activities
2025 Consumer Confidence Report (CCR)
The annual CCR has been completed and released to the customers by notification in the water bills starting in April
The 2025 CCR can be found at; https://www.orovalleyaz.gov/Government/Departments/Water-Utility/Water-Quality
OVWU Water Operations
Discussion
Water Utility Commission 7.
Meeting Date:05/11/2026
Submitted By:Meagan Ackerson, Water
SUBJECT:
UPDATE AND DISCUSSION ON WATER UTILITY FINANCIALS (M. RALLIS)
RECOMMENDATION:
n/a
EXECUTIVE SUMMARY:
n/a
BACKGROUND OR DETAILED INFORMATION:
n/a
FISCAL IMPACT:
n/a
SUGGESTED MOTION:
For discussion only
Attachments
Staff Presentation
Water Utility Commission Meeting
May 11, 2026
Oro Valley Water Utility
Update & Discussion on Water Utility
Financials
Mary Rallis, C.P.A.
Water Utility Administrator
Financial Update –Fiscal Year 2025/26 -Revenues
REVENUES Actuals
Through
3/31/26
Budget Notes
Potable Water Sales $12,983,240 $17,070,000 Projected to meet or exceed budget.
Reclaimed Water
Sales $1,050,073 $1,441,000 Projected to meet budget.
Groundwater
Preservation Fees $1,966,842 $2,600,000 Projected to meet budget.
Service Fees $644,427 $857,000 Projected to meet budget.
TOTAL REVENUES $16,644,582 $21,968,000 Revenues projected to meet budget or exceed budget.
Financial Update –Fiscal Year 2025/26 -Expenses
EXPENSES Actuals
Through
3/31/26
Budget Notes
Personnel $2,546,311 $3,985,725 Projected to be below budget due to vacancy
savings.
Operations &
Maintenance $8,241,611 $12,277,175 Projected to meet budget.
Capital $646,377 $1,602,639 Projected to be below budget.
Debt Service $3,890,977 $3,890,977 Debt service paid on 7/1/25.
TOTAL EXPENSES $15,325,276 $21,756,516 Expenses projected to be under budget due to
personnel and capital savings.
Customer Service Update –Through 4/31/26
FY 2024/25 Through 3/31/26
New meters installed 111 95
Customer base 21,609 21,704
Customer Portal 13,263 15,296
Discussion
Water Utility Commission 8.
Meeting Date:05/11/2026
Submitted By:Meagan Ackerson, Water
SUBJECT:
UPDATE AND DISCUSSION ON WATER RESOURCE USAGE (P. ABRAHAM)
RECOMMENDATION:
n/a
EXECUTIVE SUMMARY:
n/a
BACKGROUND OR DETAILED INFORMATION:
n/a
FISCAL IMPACT:
n/a
SUGGESTED MOTION:
For discussion only
Attachments
Staff Presentation
Peter A. Abraham, P.E.
Water Utility Director
Water Utility Commission
May 11, 2026
Oro Valley Water Utility
Update & Discussion on Water Resource Usage
Oro Valley Main Service Area Jan – March Water Use by Type
Countryside Service Area Jan – March Water Use by Type
Discussion
Discussion
Water Utility Commission 9.
Meeting Date:05/11/2026
Submitted By:Meagan Ackerson, Water
SUBJECT:
DIRECTOR'S REPORT
RECOMMENDATION:
n/a
EXECUTIVE SUMMARY:
n/a
BACKGROUND OR DETAILED INFORMATION:
n/a
FISCAL IMPACT:
n/a
SUGGESTED MOTION:
This item is for information only
Attachments
Director's Report
Peter A. Abraham, P.E.
Water Utility Director
Water Utility Commission Meeting
May 11, 2026
Oro Valley Water Utility
Director’s Report
Upcoming Meetings
May 20, 2026 Town Council Regular Session
Council Chambers @ 6 p.m.
June 3, 2026 Town Council Regular Session
Council Chambers @ 6 p.m.
(Public Hearing on Rates & Tentative Budget)
June 8, 2026 Water Utility Commission Meeting
Hopi Room @ 5 p.m. –Possible Cancellation
June 17, 2026 Town Council Regular Session
Council Chambers @ 6 p.m.
(Budget Adoption)
July 1, 2026 Town Council Summer Break
July 13, 2026 Water Utility Commission Meeting
Hopi Room @ 5 p.m. –Possible Cancellation
July 15, 2026 Town Council Summer Break
August 5, 2026 Town Council Summer Break
August 10, 2026 Water Utility Commission Meeting
Hopi Room @ 5 p.m.
Colorado River System Reservoir Status
Colorado River Basin Snowpack Accumulation
Thank You